Energy Projects Near You

Ashby Solar Farm (a) (5 MW)

Ashby Solar Farm (a) is a 5 MW solar farm project in North West Leicestershire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 12 March 2016; the record was last updated on 16 June 2016.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

5 MWsolar farm
operationalstatus in REPD
16 June 2016record last updated
North West Leicestershirecouncil area

Planning timeline

DateStage
26 May 2015Application submitted
9 September 2015Planning permission granted
12 December 2015Construction started
12 March 2016Operational

Project details

Technology
solar farm
Capacity
5 MW
Status (REPD)
operational
Record last updated
16 June 2016
Operator or applicant
Primrose Solar
Planning authority
North West Leicestershire
Planning application reference
15/00499/FULM
Site area
8.3 ha
Address (REPD)
Land To The East Side B4116, M, Ashby De La Zouch And, North Of Measham Rd,Packington, Ashby-De-La-Zouch
Council area (by location)
North West Leicestershire
Time to decision
15 weeks
REPD reference
5273

Who decides

ApplicationsNorth West LeicestershireUK
Decided applications (solar, wind, battery)3910,236
Refused2 (5%)19%
Solar refused2 of 3512%
Onshore wind refused0 of 245%
Battery storage refused0 of 216%
Median time from submission to decision12.0 weeks17.0 weeks
Appeals lodged / allowed0 / 0—

UK: all UK planning authorities. Counted under these REPD planning authority names: Leicestershire, North West Leicestershire.

Other large projects within 10 km

ProjectTypeMWStatuskm
Hill Farm Energy Barnbattery storage10operational1.9
Packington Solar Farmsolar farm13.9operational1.9
Prestop Park Farmsolar farm16operational3.9
Coalville solar farmsolar farm10abandoned4.0
Shortheath Solar Parksolar farm5operational4.6
Short Hazel Solar Farmsolar farm5operational6.1
Park Road, Oversealbattery storage50approved, not built6.2
Lullington Solar Parksolar farm44application submitted7.5
Mount Road, Castle Gresleybattery storage20approved, not built8.2

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.7227, -1.4853).