Packington Solar Farm (13.9 MW)

Packington Solar Farm is a 13.9 MW solar farm project in North West Leicestershire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 16 March 2015; the record was last updated on 14 May 2015.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

13.9 MWsolar farm
operationalstatus in REPD
14 May 2015record last updated
North West Leicestershirecouncil area

Planning timeline

DateStage
27 June 2014Application submitted
20 October 2014Planning permission granted
15 November 2014Construction started
16 March 2015Operational

Project details

Technology
solar farm
Capacity
13.9 MW
Status (REPD)
operational
Record last updated
14 May 2015
Operator or applicant
Solstice Renewables
Planning authority
North West Leicestershire
Planning application reference
14/00535/FULM
Site area
29.1 ha
Address (REPD)
Land South Of Babelake Street Packington Ashby De La Zouch Leicestershire LE65 1TG
Council area (by location)
North West Leicestershire
Time to decision
16 weeks
REPD reference
2054

Who decides

ApplicationsNorth West LeicestershireUK
Decided applications (solar, wind, battery)3910,236
Refused2 (5%)19%
Solar refused2 of 3512%
Onshore wind refused0 of 245%
Battery storage refused0 of 216%
Median time from submission to decision12.0 weeks17.0 weeks
Appeals lodged / allowed0 / 0—

UK: all UK planning authorities. Counted under these REPD planning authority names: Leicestershire, North West Leicestershire.

Other large projects within 10 km

ProjectTypeMWStatuskm
Ashby Solar Farm (a)solar farm5operational1.9
Hill Farm Energy Barnbattery storage10operational2.5
Coalville solar farmsolar farm10abandoned3.3
Prestop Park Farmsolar farm16operational5.8
Shortheath Solar Parksolar farm5operational6.0
Park Road, Oversealbattery storage50approved, not built7.8
Short Hazel Solar Farmsolar farm5operational8.0
Crown Farmsolar farm6operational8.5
Lullington Solar Parksolar farm44application submitted9.3

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.7073, -1.4725).