Solar, wind and battery projects near Swadlincote (DE11)
48 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of DE11 (South Derbyshire): 7 are waiting for a planning decision, 21 approved but not yet running, 13 operational. The largest live scheme is Fairfields Energy Storage System (1,025 MW battery storage, approved on 17 March 2025, not yet built), 8.1 km away. Source: Renewable Energy Planning Database, July 2026 extract.
Projects within 10 km of DE11
Projects of 1 MW and more (32)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Lullington Solar Parksolar farm | solar farm | 44 | application submittedupdated Aug 2025 | Jul 2025 | — | Aug 2025 | South Derbyshire | 0.1 |
| Land at Sunnyside Courtsolar farm | solar farm | 4.9 | refusedupdated Jan 2016 | May 2015 | refused Dec 2015 | Jan 2016 | South Derbyshire | 2.1 |
| Park Roadsolar farm | solar farm | 5 | refusedupdated May 2016 | Sep 2015 | refused Apr 2016 | May 2016 | South Derbyshire | 2.5 |
| Park Road, Oversealbattery storage | battery storage | 50 | approved, not builtupdated Dec 2025 | Oct 2024 | granted Jul 2025 | Dec 2025 | South Derbyshire | 2.5 |
| Mount Road, Castle Gresleybattery storage | battery storage | 20 | approved, not built may be out of dateupdated Nov 2021 | Nov 2021 | granted Jul 2022 | Nov 2021 | South Derbyshire | 2.9 |
| Short Hazel Solar Farmsolar farm | solar farm | 5 | operationalupdated Jul 2016 | Mar 2015 | granted Aug 2015 | Jul 2016 | South Derbyshire | 3.1 |
| Land at Coton Park Collierysolar farm | solar farm | 2.5 | operationalupdated Jul 2018 | Nov 2014 | granted Mar 2015 | Jul 2018 | South Derbyshire | 3.2 |
| Brizlincote Hall Solar Farmsolar farm | solar farm | 5 | refusedupdated Feb 2017 | Jul 2015 | refused Nov 2015 | Feb 2017 | South Derbyshire | 3.3 |
| Breach Farm Energy Barnbattery storage | battery storage | 40 | approved, not built may be out of dateupdated May 2022 | May 2017 | granted Aug 2017 | May 2022 | South Derbyshire | 3.6 |
| Prestop Park Farmsolar farm | solar farm | 16 | operationalupdated May 2018 | Jul 2014 | granted Sep 2014 | May 2018 | North West Leicestershire | 4.2 |
| Shortheath Solar Parksolar farm | solar farm | 5 | operationalupdated May 2017 | Aug 2015 | granted Dec 2015 | May 2017 | South Derbyshire | 4.7 |
| Caldwell Roadbattery storage | battery storage | 90 | approved, not builtupdated Sep 2024 | Apr 2024 | granted Jul 2024 | Sep 2024 | South Derbyshire | 4.7 |
| Land at Ingles Hill Farmsolar farm | solar farm | 3 | operationalupdated Jun 2016 | Jul 2015 | granted Sep 2015 | Jun 2016 | North West Leicestershire | 4.8 |
| Newton Solney Solar Farmsolar farm | solar farm | 21.1 | refusedupdated Dec 2025 | Aug 2024 | refused Mar 2025 | Dec 2025 | South Derbyshire | 5.1 |
| Solar Farm & Battery Storage at W/O Rosliston & E/O Walton on Trentsolar farm | solar farm | 138 | approved, not builtupdated Jun 2025 | Feb 2024 | granted Jun 2025 | Jun 2025 | South Derbyshire | 6.4 |
| Drakelow Solar Farmsolar farm | solar farm | 5 | operationalupdated Mar 2017 | Apr 2015 | granted Jun 2015 | Mar 2017 | South Derbyshire | 6.5 |
| Claymills Sewage Treatment Works, Meadow Lanesolar farm | solar farm | 25 | application submittedupdated Jul 2026 | May 2026 | — | Jul 2026 | East Staffordshire | 6.9 |
| United Biscuits Distribution Warehouserooftop solar | rooftop solar | 1 | abandonedupdated Aug 2016 | Jul 2015 | granted Sep 2015 | Aug 2016 | North West Leicestershire | 7.0 |
| Ashby Solar Farm (a)solar farm | solar farm | 5 | operationalupdated Jun 2016 | May 2015 | granted Sep 2015 | Jun 2016 | North West Leicestershire | 7.3 |
| Ashby Solar Farm (b)solar farm | solar farm | 1 | abandonedupdated Sep 2018 | May 2015 | granted Sep 2015 | Sep 2018 | North West Leicestershire | 7.3 |
| Solar Farm & Battery Storage at W/O Rosliston & E/O Walton on Trentbattery storage | battery storage | 37.5 | approved, not builtupdated Jun 2025 | Feb 2024 | granted Jun 2025 | Jun 2025 | South Derbyshire | 7.4 |
| Pirelli Limited, Derby Roadrooftop solar | rooftop solar | 1.3 | approved, not builtupdated May 2024 | Mar 2024 | granted Apr 2024 | May 2024 | East Staffordshire | 7.5 |
| Lount solar farmsolar farm | solar farm | 2.8 | operationalupdated Feb 2016 | Sep 2014 | granted Dec 2014 | Feb 2016 | North West Leicestershire | 8.0 |
| Barn Farm - Batter Energy Storage Facilitybattery storage | battery storage | 200 | approved, not builtupdated Jul 2025 | Dec 2024 | granted Jul 2025 | Jul 2025 | South Derbyshire | 8.1 |
| Fairfields Energy Storage Systembattery storage | battery storage | 1,025 | approved, not builtupdated Oct 2025 | Jun 2024 | granted Mar 2025 | Oct 2025 | South Derbyshire | 8.1 |
| Hill Farm Energy Barnbattery storage | battery storage | 10 | operationalupdated Mar 2019 | Jun 2016 | — | Mar 2019 | North West Leicestershire | 8.2 |
| Drakelowbattery storage | battery storage | 1,000 | application submittedupdated Feb 2025 | Dec 2024 | — | Feb 2025 | South Derbyshire | 8.6 |
| Mercia Park, Burton Roadrooftop solar | rooftop solar | 1 | approved, not builtupdated Mar 2023 | Feb 2023 | granted Mar 2023 | Mar 2023 | North West Leicestershire | 8.9 |
| Land at Hill Farmsolar farm | solar farm | 1.2 | operationalupdated May 2017 | Jul 2015 | granted Oct 2015 | May 2017 | North West Leicestershire | 9.1 |
| Packington Solar Farmsolar farm | solar farm | 13.9 | operationalupdated May 2015 | Jun 2014 | granted Oct 2014 | May 2015 | North West Leicestershire | 9.2 |
| Derby Road, Eggintonbattery storage | battery storage | 100 | approved, not builtupdated Jul 2025 | Apr 2024 | granted Jun 2025 | Jul 2025 | South Derbyshire | 9.4 |
| Solar Farm on land east of the A38, Willingtonsolar farm | solar farm | 3.8 | abandonedupdated Sep 2018 | Oct 2015 | granted Feb 2016 | Sep 2018 | South Derbyshire | 9.4 |
Smaller schemes under 1 MW, mostly rooftop solar (16)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Midland Lead, Kiln Wayrooftop solar | rooftop solar | 0.2 | operationalupdated Jan 2023 | Aug 2022 | granted Jan 2023 | Jan 2023 | South Derbyshire | 0.9 |
| Meadowside Leisure Centre, High Streetrooftop solar | rooftop solar | 0.3 | application submittedupdated Jan 2025 | Nov 2024 | — | Jan 2025 | East Staffordshire | 5.8 |
| Velis Kebab, Hawkins Lane - Photovoltaic Panelsrooftop solar | rooftop solar | 0.2 | approved, not builtupdated May 2024 | Mar 2024 | granted Apr 2024 | May 2024 | East Staffordshire | 6.8 |
| Burton Enterprise Park, Hawkins Lanebattery storage | battery storage | — | approved, not built may be out of dateupdated Jun 2022 | May 2022 | granted Jul 2022 | Jun 2022 | East Staffordshire | 6.8 |
| Clinitron House, Excelsior Roadrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Jun 2026 | Mar 2026 | granted May 2026 | Jun 2026 | North West Leicestershire | 7.5 |
| Ceva House, Excelsior Roadrooftop solar | rooftop solar | 0.2 | application submittedupdated Mar 2025 | Feb 2025 | — | Mar 2025 | North West Leicestershire | 7.6 |
| Stretton Business Park, Brunel Driverooftop solar | rooftop solar | — | approved, not builtupdated Apr 2025 | Feb 2025 | granted Mar 2025 | Apr 2025 | East Staffordshire | 7.7 |
| Centrum East Retail Parkrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Aug 2024 | Jun 2024 | granted Aug 2024 | Aug 2024 | East Staffordshire | 7.9 |
| Barn Farm & Walton Roadbattery storage | battery storage | — | approved, not built may be out of dateupdated Jan 2025 | Feb 2023 | granted Jul 2023 | Jan 2025 | South Derbyshire | 8.1 |
| Port Way, Branstonrooftop solar | rooftop solar | 0.7 | approved, not builtupdated Aug 2024 | May 2024 | granted Aug 2024 | Aug 2024 | East Staffordshire | 8.2 |
| Queens Hospital Burton, Belvedere Roadrooftop solar | rooftop solar | — | approved, not builtupdated Mar 2026 | Dec 2025 | granted Feb 2026 | Mar 2026 | East Staffordshire | 8.4 |
| Lanxess, Lichfield Roadrooftop solar | rooftop solar | 0.2 | application submitted may be out of dateupdated Mar 2023 | Feb 2023 | — | Mar 2023 | East Staffordshire | 8.7 |
| Twyford Road, Twyfordbattery storage | battery storage | — | application submitted | Apr 2026 | — | — | South Derbyshire | 9.1 |
| Lower Fields Mushroom Farmsolar farm | solar farm | 0.3 | operationalupdated Aug 2021 | Mar 2020 | granted Feb 2021 | Aug 2021 | North West Leicestershire | 9.1 |
| Mushroom Farm, Lower Fields - Agricultural Building & Solar Panelsrooftop solar | rooftop solar | 0.6 | approved, not builtupdated Jul 2024 | Dec 2023 | granted Jul 2024 | Jul 2024 | North West Leicestershire | 9.1 |
| DSV, Stretton En Le Fieldrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Oct 2024 | Sep 2024 | granted Oct 2024 | Oct 2024 | North West Leicestershire | 9.7 |
Distance from the average position of the DE11 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.
By type
| Type | All | Pending | Approved | Operational | Refused | MW in pipeline |
|---|---|---|---|---|---|---|
| Solar farm | 20 | 2 | 1 | 11 | 4 | 207 |
| Rooftop solar | 15 | 3 | 10 | 1 | 0 | 5 |
| Battery storage | 13 | 2 | 10 | 1 | 0 | 2,562 |
MW in pipeline: pending, approved and under-construction capacity.
How South Derbyshire decides solar, wind and battery applications
| Applications | South Derbyshire | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 26 | 10,236 |
| Refused | 5 (19%) | 19% |
| Solar refused | 4 of 14 | 12% |
| Battery storage refused | 1 of 12 | 16% |
| Median time from submission to decision | 28.6 weeks | 17.0 weeks |
| Appeals lodged / allowed | 1 / 1 | — |
All projects in South Derbyshire
Is the status up to date?
32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near DE11, 5 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.