Energy Projects Near You

Derby Road, Egginton (100 MW battery storage)

Derby Road, Egginton is a 100 MW battery storage project in South Derbyshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 24 June 2025, not yet built; the record was last updated on 28 July 2025.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

100 MWbattery storage
approved, not builtstatus in REPD
28 July 2025record last updated
South Derbyshirecouncil area

Planning timeline

DateStage
29 April 2024Application submitted
24 June 2025Planning permission granted
24 June 2030Permission due to expire (unless work starts)

Project details

Technology
battery storage (stand-alone storage)
Capacity
100 MW
Status (REPD)
approved, not built
Record last updated
28 July 2025
Operator or applicant
First Way Solar Limited
Planning authority
South Derbyshire
Planning application reference
DMPA/2024/0432
Address (REPD)
Derby Road, Egginton, Derby
Council area (by location)
South Derbyshire
Time to decision
60 weeks
Name in REPD
Derby Road, Egginton - Battery Storage Facility
REPD reference
16378

Who decides

ApplicationsSouth DerbyshireUK
Decided applications (solar, wind, battery)2610,236
Refused5 (19%)19%
Solar refused4 of 1412%
Battery storage refused1 of 1216%
Median time from submission to decision28.6 weeks17.0 weeks
Appeals lodged / allowed1 / 1—

Other large projects within 10 km

ProjectTypeMWStatuskm
Rollston on Dove, Marston Lanesolar farm5abandoned2.7
Solar Farm at Toyota Manufacturing Ukrooftop solar16application submitted3.3
Claymills Sewage Treatment Works, Meadow Lanesolar farm25application submitted3.6
Newton Solney Solar Farmsolar farm21.1refused4.5
Hoon Hay Manor, Hatton Solar Farmsolar farm5.1approved, not built4.7
Landown Farm, Bakeacre Lanebattery storage40approved, not built5.2
Rolleston Park Farmsolar farm18.7operational5.7
Rolleston Park Farm, Lodge Hill Solar Farmsolar farm12operational5.7
Brizlincote Hall Solar Farmsolar farm5refused6.9

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.8526, -1.6034).