Energy Projects Near You

Rolleston Park Farm (18.7 MW solar farm)

Rolleston Park Farm is an 18.7 MW solar farm project in East Staffordshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 31 March 2015; the record was last updated on 5 October 2015.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

18.7 MWsolar farm
operationalstatus in REPD
5 October 2015record last updated
East Staffordshirecouncil area

Planning timeline

DateStage
9 July 2014Application submitted
10 September 2014Planning permission granted
1 December 2014Construction started
31 March 2015Operational

Project details

Technology
solar farm
Capacity
18.7 MW
Status (REPD)
operational
Record last updated
5 October 2015
Operator or applicant
Push Energy
Planning authority
East Staffordshire
Planning application reference
P/2014/00830
Site area
19.9 ha
Address (REPD)
Rolleston Park Farm, Lodge Hill, Tutbury
Council area (by location)
East Staffordshire
Time to decision
9 weeks
REPD reference
2196

Who decides

ApplicationsEast StaffordshireUK
Decided applications (solar, wind, battery)2110,236
Refused1 (5%)19%
Solar refused0 of 1912%
Onshore wind refused1 of 145%
Battery storage refused0 of 116%
Median time from submission to decision11.7 weeks17.0 weeks
Appeals lodged / allowed0 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
Rolleston Park Farm, Lodge Hill Solar Farmsolar farm12operational<0.1
Hoon Hay Manor, Hatton Solar Farmsolar farm5.1approved, not built3.1
Rollston on Dove, Marston Lanesolar farm5abandoned3.2
Hawthorn Farmsolar farm10under construction3.4
Claymills Sewage Treatment Works, Meadow Lanesolar farm25application submitted4.8
Derby Road, Eggintonbattery storage100approved, not built5.7
Aston House Solar Farmsolar farm20operational6.1
Morton House (Marchington)solar farm6.2operational7.2
Land of Green Lanesolar farm5.8operational7.6

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.8397, -1.6854).