Land of Green Lane (5.8 MW solar farm)

Land of Green Lane is a 5.8 MW solar farm project in East Staffordshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 31 March 2017; the record was last updated on 20 April 2017.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

5.8 MWsolar farm
operationalstatus in REPD
20 April 2017record last updated
East Staffordshirecouncil area

Planning timeline

DateStage
3 July 2015Application submitted
23 September 2015Planning permission granted
12 December 2016Construction started
31 March 2017Operational

Project details

Technology
solar farm
Capacity
5.8 MW
Status (REPD)
operational
Record last updated
20 April 2017
Operator or applicant
TGC Renewables
Planning authority
East Staffordshire
Planning application reference
P/2015/00791
Site area
12.3 ha
Address (REPD)
Land At, Green Lane, Marchington, Uttoxeter
Council area (by location)
East Staffordshire
Time to decision
12 weeks
REPD reference
5424

Who decides

ApplicationsEast StaffordshireUK
Decided applications (solar, wind, battery)2110,236
Refused1 (5%)19%
Solar refused0 of 1912%
Onshore wind refused1 of 145%
Battery storage refused0 of 116%
Median time from submission to decision11.7 weeks17.0 weeks
Appeals lodged / allowed0 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
Morton House (Marchington)solar farm6.2operational0.4
Holtwood Farmsolar farm5operational2.3
Aston House Solar Farmsolar farm20operational2.6
Twin Oaks Farmsolar farm5abandoned3.3
Solar farm at land at The Willows, Uttoxetersolar farm6.4operational4.6
Hawthorn Farmsolar farm10under construction4.9
Bagot's Parkwind farm18.4refused7.2
Rolleston Park Farm, Lodge Hill Solar Farmsolar farm12operational7.6
Rolleston Park Farmsolar farm18.7operational7.6

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.8755, -1.781).