Solar farm at land at The Willows, Uttoxeter (6.4 MW)

Solar farm at land at The Willows, Uttoxeter is a 6.4 MW solar farm project in East Staffordshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 31 March 2017; the record was last updated on 20 April 2017.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

6.4 MWsolar farm
operationalstatus in REPD
20 April 2017record last updated
East Staffordshirecouncil area

Planning timeline

DateStage
15 April 2015Application submitted
24 July 2015Planning permission granted
12 December 2016Construction started
31 March 2017Operational

Project details

Technology
solar farm
Capacity
6.4 MW
Status (REPD)
operational
Record last updated
20 April 2017
Operator or applicant
TGC Renewables
Planning authority
East Staffordshire
Planning application reference
P/2015/00434
Site area
9.8 ha
Address (REPD)
Land South East Of The Willows, Dove Walk, Uttoxeter, Staffordshire
Council area (by location)
East Staffordshire
Time to decision
14 weeks
REPD reference
5241

Who decides

ApplicationsEast StaffordshireUK
Decided applications (solar, wind, battery)2110,236
Refused1 (5%)19%
Solar refused0 of 1912%
Onshore wind refused1 of 145%
Battery storage refused0 of 116%
Median time from submission to decision11.7 weeks17.0 weeks
Appeals lodged / allowed0 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
Twin Oaks Farmsolar farm5abandoned1.8
Holtwood Farmsolar farm5operational2.4
Land of Green Lanesolar farm5.8operational4.6
Morton House (Marchington)solar farm6.2operational4.9
Spring Farm (wind)wind farm6application withdrawn5.0
Bagot's Parkwind farm18.4refused6.1
Woodhouse Fields Farmsolar farm5operational6.2
Aston House Solar Farmsolar farm20operational6.7
Hawthorn Farmsolar farm10under construction9.4

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.896, -1.8403).