Hawthorn Farm (10 MW solar farm)

Hawthorn Farm is a 10 MW solar farm project in South Derbyshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: under construction since 1 May 2025; the record was last updated on 18 June 2025.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

10 MWsolar farm
under constructionstatus in REPD
18 June 2025record last updated
South Derbyshirecouncil area

Planning timeline

DateStage
25 March 2021Application submitted
22 February 2022Planning permission granted
1 May 2025Construction started

Project details

Technology
solar farm
Capacity
10 MW
Status (REPD)
under construction
Record last updated
18 June 2025
Operator or applicant
Unknown
Planning authority
South Derbyshire
Planning application reference
DMPA/2021/0315
Site area
9.6 ha
Address (REPD)
Land at SK1930 5342, Hawthorn Farm, Scropton Road, Scropton,
Council area (by location)
South Derbyshire
Time to decision
48 weeks
Name in REPD
Hawthorn Farm - Solar photovoltaic panels
REPD reference
8856

Who decides

ApplicationsSouth DerbyshireUK
Decided applications (solar, wind, battery)2610,236
Refused5 (19%)19%
Solar refused4 of 1412%
Battery storage refused1 of 1216%
Median time from submission to decision28.6 weeks17.0 weeks
Appeals lodged / allowed1 / 1—

Other large projects within 10 km

ProjectTypeMWStatuskm
Hoon Hay Manor, Hatton Solar Farmsolar farm5.1approved, not built2.7
Aston House Solar Farmsolar farm20operational2.8
Rolleston Park Farm, Lodge Hill Solar Farmsolar farm12operational3.4
Rolleston Park Farmsolar farm18.7operational3.4
Rollston on Dove, Marston Lanesolar farm5abandoned4.6
Morton House (Marchington)solar farm6.2operational4.6
Land of Green Lanesolar farm5.8operational4.9
Holtwood Farmsolar farm5operational7.1
Derby Road, Eggintonbattery storage100approved, not built7.3

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.8664, -1.709).