Woodhouse Fields Farm (5 MW solar farm)

Woodhouse Fields Farm is a 5 MW solar farm project in East Staffordshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 10 February 2017; the record was last updated on 19 July 2018.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

5 MWsolar farm
operationalstatus in REPD
19 July 2018record last updated
East Staffordshirecouncil area

Planning timeline

DateStage
7 August 2015Application submitted
20 November 2015Planning permission granted
10 December 2016Construction started
10 February 2017Operational

Project details

Technology
solar farm
Capacity
5 MW
Status (REPD)
operational
Record last updated
19 July 2018
Operator or applicant
Wirsol
Planning authority
East Staffordshire
Planning application reference
P/2015/01032
Site area
8.9 ha
Address (REPD)
Land To East Of, Nab Lane, Rocester, Uttoxeter
Council area (by location)
East Staffordshire
Time to decision
15 weeks
REPD reference
5577

Who decides

ApplicationsEast StaffordshireUK
Decided applications (solar, wind, battery)2110,236
Refused1 (5%)19%
Solar refused0 of 1912%
Onshore wind refused1 of 145%
Battery storage refused0 of 116%
Median time from submission to decision11.7 weeks17.0 weeks
Appeals lodged / allowed0 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
Solar farm at land at The Willows, Uttoxetersolar farm6.4operational6.2
Spring Farm (wind)wind farm6application withdrawn6.7
Twin Oaks Farmsolar farm5abandoned6.8
Tean Leys Farm, Tean Leysbattery storage70application submitted7.9
Holtwood Farmsolar farm5operational7.9
Upper Leigh Solar Farmsolar farm49.9approved, not built8.2
Moneystone Quarry Solar Farmsolar farm5operational8.3
Upper Leighbattery storage20application submitted9.0
Totmonslow Farm, Upper Tean Solar Farmsolar farm19.8approved, not built9.4

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.9491, -1.8698).