Energy Projects Near You

Upper Leigh Solar Farm (49.9 MW)

Upper Leigh Solar Farm is a 49.9 MW solar farm project in Staffordshire Moorlands, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 2 April 2024, not yet built; the record was last updated on 19 February 2026.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

49.9 MWsolar farm
approved, not builtstatus in REPD
19 February 2026record last updated
Staffordshire Moorlandscouncil area

Planning timeline

DateStage
30 January 2023Application submitted
2 April 2024Planning permission granted

Project details

Technology
solar farm
Capacity
49.9 MW
Status (REPD)
approved, not built
Record last updated
19 February 2026
Operator or applicant
Lightrock Power
Planning authority
Staffordshire Moorlands
Planning application reference
SMD/2023/0059
Site area
49.4 ha
Address (REPD)
Lower Tean Leys, Tean Leys, Lower Tean
Council area (by location)
Staffordshire Moorlands
Time to decision
61 weeks
Contracts for Difference
AR7a
REPD reference
13184

Recorded together with Upper Leigh (20 MW battery storage, application submitted).

Who decides

ApplicationsStaffordshire MoorlandsUK
Decided applications (solar, wind, battery)2510,236
Refused8 (32%)19%
Solar refused3 of 1512%
Battery storage refused5 of 1016%
Median time from submission to decision28.4 weeks17.0 weeks
Appeals lodged / allowed1 / 1—

Other large projects within 10 km

ProjectTypeMWStatuskm
Tean Leys Farm, Tean Leysbattery storage70application submitted0.4
Blythe House Farm Extensionsolar farm16.6approved, not built2.1
Upper Newton Farm (Blythe House) Solar Farm & Battery Storagebattery storage30approved, not built2.2
Lower Newton Farmsolar farm11.5operational2.2
Upper Newton Farm (Blythe House) Solar Farm & Battery Storagesolar farm27.7approved, not built2.2
Totmonslow Farm, Upper Tean Solar Farmsolar farm19.8approved, not built2.3
Solar Farm at New Buildings Solar Farmsolar farm40application submitted4.4
The Fields Farmsolar farm5refused4.5

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.9382, -1.991).