Energy Projects Near You

The Fields Farm (5 MW solar farm)

The Fields Farm is a 5 MW solar farm project in Staffordshire Moorlands, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on 21 December 2015; the record was last updated on 6 January 2016.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

5 MWsolar farm
refusedstatus in REPD
6 January 2016record last updated
Staffordshire Moorlandscouncil area

Planning timeline

DateStage
13 July 2015Application submitted
21 December 2015Refused by the planning authority

Project details

Technology
solar farm
Capacity
5 MW
Status (REPD)
refused
Record last updated
6 January 2016
Operator or applicant
Solstice Renewables
Planning authority
Staffordshire Moorlands
Planning application reference
SMD/2015/0394
Site area
11.9 ha
Address (REPD)
The Fields Farm, Draycott Cross, Cheadle, Stoke-On-Trent, Staffordshire
Council area (by location)
Staffordshire Moorlands
Time to decision
23 weeks
REPD reference
5408

Who decides

ApplicationsStaffordshire MoorlandsUK
Decided applications (solar, wind, battery)2510,236
Refused8 (32%)19%
Solar refused3 of 1512%
Battery storage refused5 of 1016%
Median time from submission to decision28.4 weeks17.0 weeks
Appeals lodged / allowed1 / 1—

Other large projects within 10 km

ProjectTypeMWStatuskm
Draycott Cross Roadbattery storage40approved, not built0.9
Totmonslow Farm, Upper Tean Solar Farmsolar farm19.8approved, not built2.2
Blythe House Farm Extensionsolar farm16.6approved, not built2.9
Upper Newton Farm (Blythe House) Solar Farm & Battery Storagebattery storage30approved, not built3.0
Lower Newton Farmsolar farm11.5operational3.0
Upper Newton Farm (Blythe House) Solar Farm & Battery Storagesolar farm27.7approved, not built3.0
Land at Heywood Grangesolar farm8.4operational3.7
Solar Farm at Leaford Solar Farmsolar farm30application submitted4.0
Tean Leys Farm, Tean Leysbattery storage70application submitted4.4

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.9739, -2.0213).