Draycott Cross Road (40 MW battery storage)

Draycott Cross Road is a 40 MW battery storage project in Staffordshire Moorlands, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 5 January 2024, not yet built; the record was last updated on 12 January 2024.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

40 MWbattery storage
approved, not builtstatus in REPD
12 January 2024record last updated
Staffordshire Moorlandscouncil area

Planning timeline

DateStage
20 June 2023Application submitted
5 January 2024Planning permission granted
5 January 2027Permission due to expire (unless work starts)

Project details

Technology
battery storage (stand-alone storage)
Capacity
40 MW
Status (REPD)
approved, not built
Record last updated
12 January 2024
Operator or applicant
Balance Power Projects Limited
Planning authority
Staffordshire Moorlands
Planning application reference
SMD/2023/0263
Address (REPD)
Draycott Cross Road, Stoke on Trent
Council area (by location)
Staffordshire Moorlands
Time to decision
28 weeks
Name in REPD
Draycott Cross Road - Battery Storage System
REPD reference
14284

Who decides

ApplicationsStaffordshire MoorlandsUK
Decided applications (solar, wind, battery)2510,236
Refused8 (32%)19%
Solar refused3 of 1512%
Battery storage refused5 of 1016%
Median time from submission to decision28.4 weeks17.0 weeks
Appeals lodged / allowed1 / 1—

Other large projects within 10 km

ProjectTypeMWStatuskm
The Fields Farmsolar farm5refused0.9
Totmonslow Farm, Upper Tean Solar Farmsolar farm19.8approved, not built2.6
Blythe House Farm Extensionsolar farm16.6approved, not built3.4
Upper Newton Farm (Blythe House) Solar Farm & Battery Storagesolar farm27.7approved, not built3.5
Upper Newton Farm (Blythe House) Solar Farm & Battery Storagebattery storage30approved, not built3.5
Lower Newton Farmsolar farm11.5operational3.5
Land at Heywood Grangesolar farm8.4operational3.9
Tean Leys Farm, Tean Leysbattery storage70application submitted4.5
Upper Leigh Solar Farmsolar farm49.9approved, not built4.7

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.9785, -2.011).