Solar, wind and battery projects near Stoke-on-Trent (ST3)
48 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of ST3 (Stoke-on-Trent): 7 are waiting for a planning decision, 32 approved but not yet running, 6 operational. The largest live scheme is Cellarhead Substation, Rownall Road (400 MW battery storage, application submitted on 13 February 2024, no decision recorded; REPD status may be out of date), 6.9 km away. Source: Renewable Energy Planning Database, July 2026 extract.
Projects within 10 km of ST3
Projects of 1 MW and more (23)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Screwfix Directrooftop solar | rooftop solar | 2.5 | operationalupdated Sep 2016 | Oct 2015 | granted Nov 2015 | Sep 2016 | Stoke-on-Trent | 3.3 |
| Land at Heywood Grangesolar farm | solar farm | 8.4 | operationalupdated Dec 2016 | Feb 2015 | granted Sep 2015 | Dec 2016 | Staffordshire Moorlands | 4.6 |
| Solar Farm at Leaford Solar Farmsolar farm | solar farm | 30 | application submitted may be out of dateupdated Jul 2024 | Jun 2024 | — | Jul 2024 | Stafford | 5.1 |
| Leek Roadsolar farm | solar farm | 1.1 | approved, not built may be out of dateupdated Dec 2021 | Nov 2021 | granted Jan 2022 | Dec 2021 | Stoke-on-Trent | 5.1 |
| Malthouse Solar Farmsolar farm | solar farm | 5 | refusedupdated Dec 2015 | Jul 2015 | refused Nov 2015 | Dec 2015 | Stafford | 5.7 |
| Leek Road, Werringtonbattery storage | battery storage | 300 | application submittedupdated Sep 2025 | Aug 2025 | — | Sep 2025 | Staffordshire Moorlands | 6.0 |
| Armshead Farm, Armshead Roadbattery storage | battery storage | 50 | approved, not builtupdated Oct 2024 | Nov 2022 | refused Jun 2023 | Oct 2024 | Staffordshire Moorlands | 6.0 |
| Royal Stoke University Hospitalrooftop solar | rooftop solar | 1 | approved, not builtupdated Nov 2025 | Aug 2025 | granted Sep 2025 | Nov 2025 | Stoke-on-Trent | 6.5 |
| The Fields Farmsolar farm | solar farm | 5 | refusedupdated Jan 2016 | Jul 2015 | refused Dec 2015 | Jan 2016 | Staffordshire Moorlands | 6.8 |
| Cellarhead Substation, Rownall Roadbattery storage | battery storage | 400 | application submitted may be out of dateupdated Apr 2024 | Feb 2024 | — | Apr 2024 | Staffordshire Moorlands | 6.9 |
| Adj New House Farm, Luzlow Lanebattery storage | battery storage | 99 | refusedupdated Jan 2026 | Feb 2025 | refused Dec 2025 | Jan 2026 | Staffordshire Moorlands | 6.9 |
| Solar Farm at New Buildings Solar Farmsolar farm | solar farm | 40 | application submittedupdated Nov 2025 | Sep 2025 | — | Nov 2025 | Staffordshire Moorlands | 7.1 |
| Cellarhead Substation, Rownall Roadbattery storage | battery storage | 2.6 | application submitted may be out of dateupdated Oct 2022 | Oct 2022 | — | Oct 2022 | Staffordshire Moorlands | 7.3 |
| Draycott Cross Roadbattery storage | battery storage | 40 | approved, not builtupdated Jan 2024 | Jun 2023 | granted Jan 2024 | Jan 2024 | Staffordshire Moorlands | 7.5 |
| Cellarhead Substation, Rownall Road Battery Energy Facilitybattery storage | battery storage | 400 | approved, not built may be out of dateupdated Jan 2023 | Aug 2022 | granted Dec 2022 | Jan 2023 | Staffordshire Moorlands | 7.6 |
| Upper Newton Farm (Blythe House) Solar Farm & Battery Storagebattery storage | battery storage | 30 | approved, not builtupdated May 2026 | Mar 2022 | granted Feb 2023 | May 2026 | Staffordshire Moorlands | 7.8 |
| Upper Newton Farm (Blythe House) Solar Farm & Battery Storagesolar farm | solar farm | 27.7 | approved, not builtupdated May 2026 | Mar 2022 | granted Feb 2023 | May 2026 | Staffordshire Moorlands | 7.8 |
| Lower Newton Farmsolar farm | solar farm | 11.5 | operationalupdated Apr 2015 | Apr 2014 | granted Aug 2014 | Apr 2015 | Staffordshire Moorlands | 7.8 |
| Blythe House Farm Extensionsolar farm | solar farm | 16.6 | approved, not builtupdated Feb 2026 | Nov 2023 | granted Jul 2024 | Feb 2026 | Staffordshire Moorlands | 8.0 |
| Newfields Farm, Rownall Roadbattery storage | battery storage | 99.9 | approved, not builtupdated Jul 2025 | Jan 2025 | granted Jul 2025 | Jul 2025 | Staffordshire Moorlands | 8.1 |
| Totmonslow Farm, Upper Tean Solar Farmsolar farm | solar farm | 19.8 | approved, not builtupdated Feb 2026 | Apr 2023 | granted Aug 2023 | Feb 2026 | Staffordshire Moorlands | 8.1 |
| Keele Universitysolar farm | solar farm | 4.4 | operationalupdated May 2022 | Dec 2018 | granted Feb 2019 | May 2022 | Newcastle-under-Lyme | 9.2 |
| Noriker Power Staunchbattery storage | battery storage | 20 | operationalupdated May 2019 | Mar 2016 | granted May 2016 | May 2019 | Newcastle-under-Lyme | 9.9 |
Smaller schemes under 1 MW, mostly rooftop solar (25)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Ormiston Meridian Academy, Sandon Roadrooftop solar | rooftop solar | 0.2 | approved, not builtupdated May 2026 | Jan 2026 | granted Mar 2026 | May 2026 | Stoke-on-Trent | 1.4 |
| Cromartie Hobbycraft, From Park Hall Road - Micro Energy Storagebattery storage | battery storage | 0.2 | application submitted | Feb 2026 | — | — | Stoke-on-Trent | 1.9 |
| VWS, Meirrooftop solar | rooftop solar | 0.4 | approved, not builtupdated Mar 2025 | Feb 2025 | granted Mar 2025 | Mar 2025 | Stoke-on-Trent | 2.0 |
| Unit 2, G-park, Whittle Roadrooftop solar | rooftop solar | 0.8 | approved, not builtupdated Jun 2022 | Jun 2022 | granted Aug 2022 | Jun 2022 | Stoke-on-Trent | 2.4 |
| Mossfield Road Solar PV Generation Systemrooftop solar | rooftop solar | 0.4 | approved, not built may be out of dateupdated Dec 2021 | Nov 2021 | granted Jan 2022 | Dec 2021 | Stoke-on-Trent | 2.6 |
| Armadillo Self Storage, Victoria Roadrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Sep 2025 | May 2025 | granted Aug 2025 | Sep 2025 | Stoke-on-Trent | 4.3 |
| Thistley Hough Academy, Thistley Houghrooftop solar | rooftop solar | 0.4 | approved, not builtupdated Jan 2026 | Oct 2025 | granted Dec 2025 | Jan 2026 | Stoke-on-Trent | 5.7 |
| Manor Bakeries, Newcastle Roadrooftop solar | rooftop solar | 0.6 | approved, not builtupdated Nov 2024 | Sep 2024 | granted Nov 2024 | Nov 2024 | Stoke-on-Trent | 6.1 |
| Barlastonbattery storage | battery storage | — | approved, not built may be out of dateupdated Apr 2022 | Dec 2021 | granted Oct 2022 | Apr 2022 | Stafford | 6.2 |
| Manor Bakeries, Newcastle Road Solar Photovoltaics Panelsrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Dec 2023 | Oct 2023 | granted Dec 2023 | Dec 2023 | Stoke-on-Trent | 6.2 |
| Arnold Clark Automobilesrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Mar 2026 | Dec 2025 | granted Feb 2026 | Mar 2026 | Stoke-on-Trent | 6.4 |
| New Buildings Farm, Sharpley Heathrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Aug 2025 | Jun 2025 | granted Aug 2025 | Aug 2025 | Staffordshire Moorlands | 7.1 |
| Greenfields Farm, Thorney Edge Roadbattery storage | battery storage | — | application submittedupdated Oct 2024 | Oct 2024 | — | Oct 2024 | Staffordshire Moorlands | 7.2 |
| Workshop, Croft Roadrooftop solar | rooftop solar | 0.2 | approved, not builtupdated May 2025 | Mar 2025 | granted Apr 2025 | May 2025 | Newcastle-under-Lyme | 8.1 |
| The 4 Candles, High Streetrooftop solar | rooftop solar | — | approved, not builtupdated Jun 2023 | Apr 2023 | granted Jun 2023 | Jun 2023 | Newcastle-under-Lyme | 8.6 |
| The 4 Candles, High Streetbattery storage | battery storage | — | approved, not builtupdated Jun 2023 | Apr 2023 | granted Jun 2023 | Jun 2023 | Newcastle-under-Lyme | 8.6 |
| Ford Green Trade Centre, Ford Green Roadrooftop solar | rooftop solar | 0.3 | approved, not builtupdated Jan 2026 | Sep 2025 | granted Oct 2025 | Jan 2026 | Stoke-on-Trent | 8.8 |
| Keele Universitybattery storage | battery storage | — | operationalupdated May 2022 | Dec 2018 | granted Sep 2019 | May 2022 | Newcastle-under-Lyme | 9.2 |
| Central Food, Unicorn Industrial Estaterooftop solar | rooftop solar | 0.3 | approved, not builtupdated May 2023 | Mar 2023 | granted Apr 2023 | May 2023 | Stoke-on-Trent | 9.3 |
| Consall Hall Gardenssolar farm | solar farm | 0.3 | approved, not builtupdated Nov 2025 | Feb 2024 | granted Apr 2025 | Nov 2025 | Staffordshire Moorlands | 9.4 |
| Arnold Clark Automobiles Limited, Brymbo Roadrooftop solar | rooftop solar | 0.3 | approved, not builtupdated May 2026 | Feb 2026 | granted Mar 2026 | May 2026 | Newcastle-under-Lyme | 9.6 |
| Haywood Hospital, High Lane Solar Canopyrooftop solar | rooftop solar | — | approved, not builtupdated Nov 2025 | Mar 2025 | granted May 2025 | Nov 2025 | Stoke-on-Trent | 9.6 |
| Tree Of Life, Coaldale Roadrooftop solar | rooftop solar | 0.5 | approved, not builtupdated Jun 2023 | Apr 2023 | granted May 2023 | Jun 2023 | Newcastle-under-Lyme | 9.9 |
| Coaldale Road & Ore Close, Lymedale Business Park - Micro Energy Storagebattery storage | battery storage | 0.2 | approved, not builtupdated May 2026 | Feb 2026 | granted Mar 2026 | May 2026 | Newcastle-under-Lyme | 9.9 |
| Tunstall Trade Park, Brownhills Roadrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Mar 2024 | Jan 2024 | granted Feb 2024 | Mar 2024 | Stoke-on-Trent | 10.0 |
Distance from the average position of the ST3 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.
By type
| Type | All | Pending | Approved | Operational | Refused | MW in pipeline |
|---|---|---|---|---|---|---|
| Solar farm | 12 | 2 | 5 | 3 | 2 | 135 |
| Rooftop solar | 20 | 0 | 19 | 1 | 0 | 6.4 |
| Battery storage | 16 | 5 | 8 | 2 | 1 | 1,323 |
MW in pipeline: pending, approved and under-construction capacity.
How Stoke-on-Trent decides solar, wind and battery applications
| Applications | Stoke-on-Trent | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 20 | 10,236 |
| Refused | 2 (10%) | 19% |
| Solar refused | 2 of 20 | 12% |
| Median time from submission to decision | 7.5 weeks | 17.0 weeks |
| Appeals lodged / allowed | 0 / 1 | — |
All projects in Stoke-on-Trent
Is the status up to date?
32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near ST3, 7 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.