Energy Projects Near You

Upper Newton Farm (Blythe House) Solar Farm & Battery Storage (27.7 MW)

Upper Newton Farm (Blythe House) Solar Farm & Battery Storage is a 27.7 MW solar farm project in Staffordshire Moorlands, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 1 February 2023, not yet built; the record was last updated on 7 May 2026.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

27.7 MWsolar farm
approved, not builtstatus in REPD
7 May 2026record last updated
Staffordshire Moorlandscouncil area

Planning timeline

DateStage
24 March 2022Application submitted
1 February 2023Planning permission granted
28 February 2028Permission due to expire (unless work starts)

Project details

Technology
solar farm
Capacity
27.7 MW
Status (REPD)
approved, not built
Record last updated
7 May 2026
Operator or applicant
Innova Renewables
Planning authority
Staffordshire Moorlands
Planning application reference
SMD/2022/0160
Site area
42.2 ha
Address (REPD)
Upper Newton Farm, Draycott Road, Upper Tean
Council area (by location)
Staffordshire Moorlands
Time to decision
45 weeks
Contracts for Difference
AR7a
Name in REPD
Upper Newton Farm (Blythe House) - Solar Farm & Battery Storage
REPD reference
10977

The scheme also includes 27.7 MW of solar farm, recorded separately in REPD (approved, not built).

Who decides

ApplicationsStaffordshire MoorlandsUK
Decided applications (solar, wind, battery)2510,236
Refused8 (32%)19%
Solar refused3 of 1512%
Battery storage refused5 of 1016%
Median time from submission to decision28.4 weeks17.0 weeks
Appeals lodged / allowed1 / 1—

Other large projects within 10 km

ProjectTypeMWStatuskm
Lower Newton Farmsolar farm11.5operational<0.1
Upper Newton Farm (Blythe House) Solar Farm & Battery Storagebattery storage30approved, not built<0.1
Blythe House Farm Extensionsolar farm16.6approved, not built0.2
Totmonslow Farm, Upper Tean Solar Farmsolar farm19.8approved, not built1.1
Upper Leigh Solar Farmsolar farm49.9approved, not built2.2
Tean Leys Farm, Tean Leysbattery storage70application submitted2.4
Solar Farm at New Buildings Solar Farmsolar farm40application submitted2.9
Upper Leighbattery storage20application submitted3.0
The Fields Farmsolar farm5refused3.0

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.9473, -2.0203).