Energy Projects Near You

Solar Farm at New Buildings Solar Farm (40 MW)

Solar Farm at New Buildings Solar Farm is a 40 MW solar farm project in Staffordshire Moorlands, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: application submitted on 30 September 2025, no decision recorded; the record was last updated on 6 November 2025.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

40 MWsolar farm
application submittedstatus in REPD
6 November 2025record last updated
Staffordshire Moorlandscouncil area

Planning timeline

DateStage
30 September 2025Application submitted

Project details

Technology
solar farm
Capacity
40 MW
Status (REPD)
application submitted
Record last updated
6 November 2025
Operator or applicant
New Buildings Solar Farm Limited
Planning authority
Staffordshire Moorlands
Planning application reference
SMD/2025/0388
Site area
102.5 ha
Address (REPD)
New Buildings Solar Farm, Sandon Road, Hilderstone
Council area (by location)
Staffordshire Moorlands
Name in REPD
New Buildings Solar Farm, Sandon Road - Solar Farm
REPD reference
12252

Who decides

ApplicationsStaffordshire MoorlandsUK
Decided applications (solar, wind, battery)2510,236
Refused8 (32%)19%
Solar refused3 of 1512%
Battery storage refused5 of 1016%
Median time from submission to decision28.4 weeks17.0 weeks
Appeals lodged / allowed1 / 1—

Other large projects within 10 km

ProjectTypeMWStatuskm
Solar Farm at Leaford Solar Farmsolar farm30application submitted2.3
Upper Newton Farm (Blythe House) Solar Farm & Battery Storagebattery storage30approved, not built2.9
Upper Newton Farm (Blythe House) Solar Farm & Battery Storagesolar farm27.7approved, not built2.9
Lower Newton Farmsolar farm11.5operational2.9
Blythe House Farm Extensionsolar farm16.6approved, not built3.2
Upper Leighbattery storage20application submitted3.9
Totmonslow Farm, Upper Tean Solar Farmsolar farm19.8approved, not built4.1
Upper Leigh Solar Farmsolar farm49.9approved, not built4.4
Tean Leys Farm, Tean Leysbattery storage70application submitted4.7

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.9313, -2.0552).