Solar, wind and battery projects near Stoke-on-Trent (ST12)
29 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of ST12 (Stafford): 4 are waiting for a planning decision, 19 approved but not yet running, 5 operational. The largest live scheme is Solar Farm at New Buildings Solar Farm (40 MW solar farm, application submitted on 30 September 2025, no decision recorded), 8.1 km away. Source: Renewable Energy Planning Database, July 2026 extract.
Projects within 10 km of ST12
Projects of 1 MW and more (11)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Malthouse Solar Farmsolar farm | solar farm | 5 | refusedupdated Dec 2015 | Jul 2015 | refused Nov 2015 | Dec 2015 | Stafford | 0.9 |
| Screwfix Directrooftop solar | rooftop solar | 2.5 | operationalupdated Sep 2016 | Oct 2015 | granted Nov 2015 | Sep 2016 | Stoke-on-Trent | 3.1 |
| Newcastle Road, Cotes Heathsolar farm | solar farm | 15 | application submittedupdated Sep 2025 | Jul 2025 | — | Sep 2025 | Stafford | 6.5 |
| Royal Stoke University Hospitalrooftop solar | rooftop solar | 1 | approved, not builtupdated Nov 2025 | Aug 2025 | granted Sep 2025 | Nov 2025 | Stoke-on-Trent | 6.8 |
| Solar Farm at Leaford Solar Farmsolar farm | solar farm | 30 | application submitted may be out of dateupdated Jul 2024 | Jun 2024 | — | Jul 2024 | Stafford | 7.1 |
| Keele Universitysolar farm | solar farm | 4.4 | operationalupdated May 2022 | Dec 2018 | granted Feb 2019 | May 2022 | Newcastle-under-Lyme | 7.9 |
| Solar Farm at New Buildings Solar Farmsolar farm | solar farm | 40 | application submittedupdated Nov 2025 | Sep 2025 | — | Nov 2025 | Staffordshire Moorlands | 8.1 |
| Leek Roadsolar farm | solar farm | 1.1 | approved, not built may be out of dateupdated Dec 2021 | Nov 2021 | granted Jan 2022 | Dec 2021 | Stoke-on-Trent | 8.3 |
| Aspley House Farm, Aspley Lanebattery storage | battery storage | 10 | approved, not built may be out of dateupdated Feb 2023 | Oct 2022 | granted Jan 2023 | Feb 2023 | Stafford | 8.9 |
| The Low Carbon Energy Generation Project at Keele Universitywind farm | wind farm | 1.9 | operationalupdated Sep 2021 | Dec 2018 | granted May 2019 | Sep 2021 | Newcastle-under-Lyme | 9.0 |
| Land at Heywood Grangesolar farm | solar farm | 8.4 | operationalupdated Dec 2016 | Feb 2015 | granted Sep 2015 | Dec 2016 | Staffordshire Moorlands | 9.3 |
Smaller schemes under 1 MW, mostly rooftop solar (18)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Barlastonbattery storage | battery storage | — | approved, not built may be out of dateupdated Apr 2022 | Dec 2021 | granted Oct 2022 | Apr 2022 | Stafford | 1.6 |
| Ormiston Meridian Academy, Sandon Roadrooftop solar | rooftop solar | 0.2 | approved, not builtupdated May 2026 | Jan 2026 | granted Mar 2026 | May 2026 | Stoke-on-Trent | 5.3 |
| VWS, Meirrooftop solar | rooftop solar | 0.4 | approved, not builtupdated Mar 2025 | Feb 2025 | granted Mar 2025 | Mar 2025 | Stoke-on-Trent | 5.8 |
| Manor Bakeries, Newcastle Roadrooftop solar | rooftop solar | 0.6 | approved, not builtupdated Nov 2024 | Sep 2024 | granted Nov 2024 | Nov 2024 | Stoke-on-Trent | 6.0 |
| Manor Bakeries, Newcastle Road Solar Photovoltaics Panelsrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Dec 2023 | Oct 2023 | granted Dec 2023 | Dec 2023 | Stoke-on-Trent | 6.0 |
| Unit 2, G-park, Whittle Roadrooftop solar | rooftop solar | 0.8 | approved, not builtupdated Jun 2022 | Jun 2022 | granted Aug 2022 | Jun 2022 | Stoke-on-Trent | 6.1 |
| Thistley Hough Academy, Thistley Houghrooftop solar | rooftop solar | 0.4 | approved, not builtupdated Jan 2026 | Oct 2025 | granted Dec 2025 | Jan 2026 | Stoke-on-Trent | 6.1 |
| Cromartie Hobbycraft, From Park Hall Road - Micro Energy Storagebattery storage | battery storage | 0.2 | application submitted | Feb 2026 | — | — | Stoke-on-Trent | 6.7 |
| Mossfield Road Solar PV Generation Systemrooftop solar | rooftop solar | 0.4 | approved, not built may be out of dateupdated Dec 2021 | Nov 2021 | granted Jan 2022 | Dec 2021 | Stoke-on-Trent | 6.9 |
| Armadillo Self Storage, Victoria Roadrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Sep 2025 | May 2025 | granted Aug 2025 | Sep 2025 | Stoke-on-Trent | 7.0 |
| Brooms Road - Micro Energy Storagebattery storage | battery storage | 0.2 | approved, not builtupdated May 2026 | Oct 2025 | granted Mar 2026 | May 2026 | Stafford | 7.1 |
| Aston Marina, Lichfield Roadsolar farm | solar farm | 0.3 | approved, not builtupdated Jan 2025 | Apr 2024 | granted Dec 2024 | Jan 2025 | Stafford | 7.6 |
| Keele Universitybattery storage | battery storage | — | operationalupdated May 2022 | Dec 2018 | granted Sep 2019 | May 2022 | Newcastle-under-Lyme | 7.9 |
| New Buildings Farm, Sharpley Heathrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Aug 2025 | Jun 2025 | granted Aug 2025 | Aug 2025 | Staffordshire Moorlands | 8.0 |
| Arnold Clark Automobilesrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Mar 2026 | Dec 2025 | granted Feb 2026 | Mar 2026 | Stoke-on-Trent | 8.4 |
| Workshop, Croft Roadrooftop solar | rooftop solar | 0.2 | approved, not builtupdated May 2025 | Mar 2025 | granted Apr 2025 | May 2025 | Newcastle-under-Lyme | 8.7 |
| The 4 Candles, High Streetrooftop solar | rooftop solar | — | approved, not builtupdated Jun 2023 | Apr 2023 | granted Jun 2023 | Jun 2023 | Newcastle-under-Lyme | 10.0 |
| The 4 Candles, High Streetbattery storage | battery storage | — | approved, not builtupdated Jun 2023 | Apr 2023 | granted Jun 2023 | Jun 2023 | Newcastle-under-Lyme | 10.0 |
Distance from the average position of the ST12 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.
By type
| Type | All | Pending | Approved | Operational | Refused | MW in pipeline |
|---|---|---|---|---|---|---|
| Solar farm | 8 | 3 | 2 | 2 | 1 | 86.4 |
| Rooftop solar | 14 | 0 | 13 | 1 | 0 | 4.8 |
| Wind farm | 1 | 0 | 0 | 1 | 0 | 0 |
| Battery storage | 6 | 1 | 4 | 1 | 0 | 10.4 |
MW in pipeline: pending, approved and under-construction capacity.
How Stafford decides solar, wind and battery applications
| Applications | Stafford | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 20 | 10,236 |
| Refused | 5 (25%) | 19% |
| Solar refused | 3 of 14 | 12% |
| Onshore wind refused | 1 of 1 | 45% |
| Battery storage refused | 1 of 5 | 16% |
| Median time from submission to decision | 16.3 weeks | 17.0 weeks |
| Appeals lodged / allowed | 2 / 2 | — |
Is the status up to date?
32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near ST12, 5 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.