Renewable energy projects in Stafford

29 solar, wind or battery projects of 150 kW or more are located in Stafford (REPD, July 2026 extract): 7 pending, 18 approved but not running, 0 operational and 3 refused. The council refused 5 of 20 decided applications (25%; UK 19%), with a median 16 weeks from submission to decision.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

29projects in the council area
7awaiting a decision
18approved, not running
25%of decisions refused

How Stafford decides

ApplicationsStaffordUK
Decided applications (solar, wind, battery)2010,236
Refused5 (25%)19%
Solar refused3 of 1412%
Onshore wind refused1 of 145%
Battery storage refused1 of 516%
Median time from submission to decision16.3 weeks17.0 weeks
Appeals lodged / allowed2 / 2—

Projects in Stafford

Projects of 1 MW and more (15)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updated
Flashbrook Road, Knighton Solar Farmsolar farmsolar farm49.9application submitted may be out of dateupdated Mar 2024Feb 2024—Mar 2024
Lower Farm, Drointon Lane Solar farm & Battery Energy Storagesolar farmsolar farm49.9approved, not builtupdated Feb 2026Mar 2023granted Jan 2025Feb 2026
Hanyards Lane, Tixall Solar Energy Parksolar farmsolar farm49.5approved, not builtupdated Sep 2025Jun 2023granted Jun 2024Sep 2025
Yew Tree Farm, Drointon Lanesolar farmsolar farm49application submittedupdated Jun 2025May 2025—Jun 2025
Wincote Farm, Wincote Lane Solar Farmsolar farmsolar farm30.2application submitted may be out of dateupdated May 2023Mar 2023—May 2023
Lower Farm, Drointon Lane Solar farm & Battery Energy Storagebattery storagebattery storage30approved, not builtupdated Feb 2026Mar 2023granted Jan 2025Feb 2026
Yew Tree Farm, Drointon Lanebattery storagebattery storage30application submittedupdated Jun 2025May 2025—Jun 2025
Solar Farm at Leaford Solar Farmsolar farmsolar farm30application submitted may be out of dateupdated Jul 2024Jun 2024—Jul 2024
Flashbrook Road, Knighton Solar Farmbattery storagebattery storage15application submitted may be out of dateupdated Mar 2024Feb 2024—Mar 2024
Newcastle Road, Cotes Heathsolar farmsolar farm15application submittedupdated Sep 2025Jul 2025—Sep 2025
Aspley House Farm, Aspley Lanebattery storagebattery storage10approved, not built may be out of dateupdated Feb 2023Oct 2022granted Jan 2023Feb 2023
Knightley Hall Wind Farmwind farmwind farm6refusedupdated Feb 2015Jun 2014refused Jan 2015Feb 2015
Malthouse Solar Farmsolar farmsolar farm5refusedupdated Dec 2015Jul 2015refused Nov 2015Dec 2015
Tunstall Hall Farmsolar farmsolar farm5refusedupdated Jan 2016Sep 2015refused Dec 2015Jan 2016
Unit DC 1 - Screwfix Directrooftop solarrooftop solar1.8application withdrawnupdated Dec 2015Sep 2015—Dec 2015
Smaller schemes under 1 MW, mostly rooftop solar (14)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updated
Pets at Home Distribution Centre, Stone Roadrooftop solarrooftop solar0.9approved, not builtupdated Jan 2024Nov 2023granted Dec 2023Jan 2024
Church Lane, Hixonrooftop solarrooftop solar0.7approved, not builtupdated Jan 2022Jun 2021granted Jan 2022Jan 2022
Alpha Manufacturing, Pasturefieldsrooftop solarrooftop solar0.7approved, not builtupdated May 2022May 2022granted Jul 2022May 2022
County Hospital, Weston Roadrooftop solarrooftop solar0.7approved, not builtupdated Sep 2025Jul 2025granted Sep 2025Sep 2025
Aston Marina, Lichfield Roadsolar farmsolar farm0.3approved, not builtupdated Jan 2025Apr 2024granted Dec 2024Jan 2025
Stafford Leisure Centre, Lammascote Roadrooftop solarrooftop solar0.3under constructionupdated Dec 2025Oct 2024granted Dec 2024Dec 2025
Sainsburys, Chell Roadrooftop solarrooftop solar0.2approved, not builtupdated May 2025Mar 2025granted Apr 2025May 2025
Fernhill Farm, Fernhill Roadsolar farmsolar farm0.2approved, not builtupdated Sep 2024Jun 2024granted Sep 2024Sep 2024
Brooms Road - Micro Energy Storagebattery storagebattery storage0.2approved, not builtupdated May 2026Oct 2025granted Mar 2026May 2026
West Midlands Ambulance Service, Tollgate Driverooftop solarrooftop solar0.1approved, not builtupdated Mar 2025Jan 2025granted Feb 2025Mar 2025
Staffordshire Police Authority, Weston Roadrooftop solarrooftop solar0.1approved, not builtupdated Oct 2025Aug 2025granted Sep 2025Oct 2025
Stafford Manor High School, Rising Brookrooftop solarrooftop solar0.1approved, not builtupdated Dec 2025Oct 2025granted Nov 2025Dec 2025
Barlastonbattery storagebattery storage—approved, not built may be out of dateupdated Apr 2022Dec 2021granted Oct 2022Apr 2022
Grey Friars Waybattery storagebattery storage—approved, not builtupdated Apr 2024May 2023granted Mar 2024Apr 2024

Postcode districts in Stafford

DistrictProjects within 10 kmPendingApprovedOperational
ST12294195
ST15184111
ST16180170
ST17190161
ST18222190
ST209310
ST2114460

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Projects belong to Stafford by location (nearest postcode to the REPD grid reference); decisions are counted by the planning authority named in REPD.