Hanyards Lane, Tixall Solar Energy Park (49.5 MW)

Hanyards Lane, Tixall Solar Energy Park is a 49.5 MW solar farm project in Stafford, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 19 June 2024, not yet built; the record was last updated on 29 September 2025.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

49.5 MWsolar farm
approved, not builtstatus in REPD
29 September 2025record last updated
Staffordcouncil area

Planning timeline

DateStage
1 June 2023Application submitted
19 June 2024Planning permission granted
19 June 2027Permission due to expire (unless work starts)

Project details

Technology
solar farm
Capacity
49.5 MW
Status (REPD)
approved, not built
Record last updated
29 September 2025
Operator or applicant
Private Developer
Planning authority
Stafford
Planning application reference
23/37621/FUL
Site area
62.0 ha
Address (REPD)
North Of Hanyards Lane Tixall
Council area (by location)
Stafford
Time to decision
55 weeks
Name in REPD
Hanyards Lane, Tixall - Solar Energy Park
REPD reference
13140

Who decides

ApplicationsStaffordUK
Decided applications (solar, wind, battery)2010,236
Refused5 (25%)19%
Solar refused3 of 1412%
Onshore wind refused1 of 145%
Battery storage refused1 of 516%
Median time from submission to decision16.3 weeks17.0 weeks
Appeals lodged / allowed2 / 2—

Other large projects within 10 km

ProjectTypeMWStatuskm
Lower Farm, Drointon Lane Solar farm & Battery Energy Storagesolar farm49.9approved, not built7.1
Yew Tree Farm, Drointon Lanesolar farm49application submitted7.3
Moreton Brook Farm, Lea Lane Solar Farmsolar farm49.9approved, not built7.8
Littywood Farm, Toft Lanesolar farm40approved, not built9.8

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.8136, -2.0586).