Littywood Farm, Toft Lane (40 MW solar farm)

Littywood Farm, Toft Lane is a 40 MW solar farm project in South Staffordshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 28 October 2024, not yet built; the record was last updated on 16 February 2026.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

40 MWsolar farm
approved, not builtstatus in REPD
16 February 2026record last updated
South Staffordshirecouncil area

Planning timeline

DateStage
5 December 2022Application submitted
22 September 2023Refused by the planning authority
28 October 2024Appeal allowed

Project details

Technology
solar farm
Capacity
40 MW
Status (REPD)
approved, not built
Record last updated
16 February 2026
Operator or applicant
Elgin Energy Services
Planning authority
South Staffordshire
Planning application reference
22/00936/FUL
Site area
70.7 ha
Address (REPD)
Littywood Farm, Toft Lane, Coppenhall, Stafford
Council area (by location)
South Staffordshire
Time to decision
42 weeks
Contracts for Difference
AR7a
Name in REPD
Littywood Farm, Toft Lane - Solar Array
REPD reference
12981

Who decides

ApplicationsSouth StaffordshireUK
Decided applications (solar, wind, battery)4310,236
Refused7 (16%)19%
Solar refused1 of 1712%
Onshore wind refused2 of 345%
Battery storage refused4 of 2316%
Median time from submission to decision22.9 weeks17.0 weeks
Appeals lodged / allowed2 / 3—

Other large projects within 10 km

ProjectTypeMWStatuskm
Levedale Road, Levedalebattery storage50approved, not built0.6
Preston Hill Farm, Penkridge Solar Farmsolar farm49.9approved, not built2.3
Four Ashes, Deepmore Lane Solar Farmsolar farm22.5approved, not built8.2
King's Streetwind farm12refused8.5
Upper Latherford Farm, Latherford Lanebattery storage50approved, not built9.5
Hanyards Lane, Tixall Solar Energy Parksolar farm49.5approved, not built9.8

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.745, -2.1503).