Levedale Road, Levedale (50 MW battery storage)

Levedale Road, Levedale is a 50 MW battery storage project in South Staffordshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 6 December 2024, not yet built; the record was last updated on 13 January 2025.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

50 MWbattery storage
approved, not builtstatus in REPD
13 January 2025record last updated
South Staffordshirecouncil area

Planning timeline

DateStage
21 March 2023Application submitted
23 November 2023Refused by the planning authority
20 May 2024Appeal lodged
6 December 2024Planning permission granted
6 December 2024Appeal allowed
6 December 2027Permission due to expire (unless work starts)

Project details

Technology
battery storage (stand-alone storage)
Capacity
50 MW
Status (REPD)
approved, not built
Record last updated
13 January 2025
Operator or applicant
Anglo Renewables Limited
Planning authority
South Staffordshire
Planning application reference
23/00145/FUL
Appeal reference
24/00021/REF
Address (REPD)
Land On South West Side Of Levedale Road
Council area (by location)
South Staffordshire
Time to decision
89 weeks
Contracts for Difference
AR6
Name in REPD
Levedale Road, Levedale - Battery Energy Storage
REPD reference
13615

Who decides

ApplicationsSouth StaffordshireUK
Decided applications (solar, wind, battery)4310,236
Refused7 (16%)19%
Solar refused1 of 1712%
Onshore wind refused2 of 345%
Battery storage refused4 of 2316%
Median time from submission to decision22.9 weeks17.0 weeks
Appeals lodged / allowed2 / 3—

Other large projects within 10 km

ProjectTypeMWStatuskm
Littywood Farm, Toft Lanesolar farm40approved, not built0.6
Preston Hill Farm, Penkridge Solar Farmsolar farm49.9approved, not built1.7
Four Ashes, Deepmore Lane Solar Farmsolar farm22.5approved, not built7.6
King's Streetwind farm12refused8.5
Upper Latherford Farm, Latherford Lanebattery storage50approved, not built9.0
Chillington Estate, Chillington Parksolar farm40approved, not built9.8

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.7399, -2.1486).