Energy Projects Near You

Preston Hill Farm, Penkridge Solar Farm (49.9 MW)

Preston Hill Farm, Penkridge Solar Farm is a 49.9 MW solar farm project in South Staffordshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 2 February 2024, not yet built; the record was last updated on 7 May 2026.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

49.9 MWsolar farm
approved, not builtstatus in REPD
7 May 2026record last updated
South Staffordshirecouncil area

Planning timeline

DateStage
9 January 2023Application submitted
2 February 2024Planning permission granted
2 February 2027Permission due to expire (unless work starts)

Project details

Technology
solar farm
Capacity
49.9 MW
Status (REPD)
approved, not built
Record last updated
7 May 2026
Operator or applicant
Engena Limited
Planning authority
South Staffordshire
Planning application reference
23/00009/FUL
Site area
61.8 ha
Address (REPD)
Preston Hill Farm Preston Vale Penkridge
Council area (by location)
South Staffordshire
Time to decision
56 weeks
Name in REPD
Preston Hill Farm, Penkridge - Solar Farm
REPD reference
10779

Who decides

ApplicationsSouth StaffordshireUK
Decided applications (solar, wind, battery)4310,236
Refused7 (16%)19%
Solar refused1 of 1712%
Onshore wind refused2 of 345%
Battery storage refused4 of 2316%
Median time from submission to decision22.9 weeks17.0 weeks
Appeals lodged / allowed2 / 3—

Other large projects within 10 km

ProjectTypeMWStatuskm
Levedale Road, Levedalebattery storage50approved, not built1.7
Littywood Farm, Toft Lanesolar farm40approved, not built2.3
Four Ashes, Deepmore Lane Solar Farmsolar farm22.5approved, not built6.0
Upper Latherford Farm, Latherford Lanebattery storage50approved, not built7.3
Oaklands Farm, New Roadbattery storage70approved, not built8.4
Lawn Lane, Coven Solar Farmsolar farm48approved, not built8.6
Chillington Estate, Chillington Parksolar farm40approved, not built8.8
New Road, Featherstonebattery storage100application withdrawn9.3
King's Streetwind farm12refused9.4

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.7265, -2.1363).