King's Street (12 MW wind farm)

King's Street is a 12 MW wind farm project in South Staffordshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on 6 April 2011; the record was last updated on 9 August 2011.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

12 MWwind farm
refusedstatus in REPD
9 August 2011record last updated
South Staffordshirecouncil area

Planning timeline

DateStage
13 December 2010Application submitted
6 April 2011Refused by the planning authority

Project details

Technology
wind farm
Capacity
12 MW
Status (REPD)
refused
Record last updated
9 August 2011
Operator or applicant
Wind Prospect
Planning authority
South Staffordshire
Planning application reference
10/00963/FUL
Turbines
6
Address (REPD)
King's Street, Brineton, Staffordshire.
Council area (by location)
South Staffordshire
Time to decision
16 weeks
REPD reference
3601

Who decides

ApplicationsSouth StaffordshireUK
Decided applications (solar, wind, battery)4310,236
Refused7 (16%)19%
Solar refused1 of 1712%
Onshore wind refused2 of 345%
Battery storage refused4 of 2316%
Median time from submission to decision22.9 weeks17.0 weeks
Appeals lodged / allowed2 / 3—

Other large projects within 10 km

ProjectTypeMWStatuskm
Sheriffhales Solar Farmsolar farm8.2operational7.0
Knightley Hall Wind Farmwind farm6refused7.8
Littywood Farm, Toft Lanesolar farm40approved, not built8.5
Levedale Road, Levedalebattery storage50approved, not built8.5
Preston Hill Farm, Penkridge Solar Farmsolar farm49.9approved, not built9.4
Chillington Estate, Chillington Parksolar farm40approved, not built9.6
Granville Road Solar Farmsolar farm5operational9.6

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.7329, -2.2749).