Solar, wind and battery projects near Stafford (ST19)

32 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of ST19 (South Staffordshire): 1 is waiting for a planning decision, 23 approved but not yet running, 4 operational. The largest live scheme is Oaklands Farm, New Road (70 MW battery storage, approved on 22 August 2024, not yet built; REPD status may be out of date), 6.8 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

32projects within 10 km
1awaiting a decision
23approved, not running
4operational

Projects within 10 km of ST19

Projects of 1 MW and more (16)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Preston Hill Farm, Penkridge Solar Farmsolar farmsolar farm49.9approved, not builtupdated May 2026Jan 2023granted Feb 2024May 2026South Staffordshire2.1
Rodbastonwind farmwind farm4operationalupdated Apr 2017Jul 2009granted Dec 2010Apr 2017South Staffordshire2.2
Levedale Road, Levedalebattery storagebattery storage50approved, not builtupdated Jan 2025Mar 2023granted Dec 2024Jan 2025South Staffordshire3.5
Littywood Farm, Toft Lanesolar farmsolar farm40approved, not builtupdated Feb 2026Dec 2022refused Sep 2023Feb 2026South Staffordshire4.0
Four Ashes, Deepmore Lane Solar Farmsolar farmsolar farm22.5approved, not builtupdated Aug 2024Oct 2023granted Jul 2024Aug 2024South Staffordshire4.3
Barr Farmsolar farmsolar farm1.8operationalupdated Apr 2015Jun 2014granted Aug 2014Apr 2015South Staffordshire4.6
Upper Latherford Farm, Latherford Lanebattery storagebattery storage50approved, not builtupdated Nov 2024Nov 2023granted Oct 2024Nov 2024South Staffordshire5.9
Lawn Lane, Coven Solar Farmsolar farmsolar farm48approved, not builtupdated Feb 2026Dec 2023granted Aug 2024Feb 2026South Staffordshire6.6
Chillington Estate, Chillington Parksolar farmsolar farm40approved, not builtupdated Feb 2026Nov 2023granted Jul 2025Feb 2026South Staffordshire6.7
Chillington Estate, Chillington Parkbattery storagebattery storage40approved, not builtupdated Feb 2026Nov 2023granted Jul 2025Feb 2026South Staffordshire6.7
Oaklands Farm, New Roadbattery storagebattery storage70approved, not built may be out of dateupdated Sep 2024Dec 2023granted Aug 2024Sep 2024South Staffordshire6.8
Land East of Lawn Lanesolar farmsolar farm5operationalupdated Aug 2016Aug 2015granted Nov 2015Aug 2016South Staffordshire7.6
New Road, Featherstonebattery storagebattery storage100application withdrawnupdated Jul 2025Dec 2023—Jul 2025South Staffordshire7.7
Jaguar Land Roverrooftop solarrooftop solar5.8operationalupdated Dec 2014May 2014granted Aug 2014Dec 2014South Staffordshire8.4
Valiant Way, Pendefordrooftop solarrooftop solar1.2approved, not built may be out of dateupdated Dec 2021Aug 2021granted Nov 2021Dec 2021South Staffordshire8.5
King's Streetwind farmwind farm12refusedupdated Aug 2011Dec 2010refused Apr 2011Aug 2011South Staffordshire9.0
Smaller schemes under 1 MW, mostly rooftop solar (16)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Saxon Road - Micro Energy Storage Facilitybattery storagebattery storage0.2refusedupdated Sep 2025Mar 2025refused Sep 2025Sep 2025South Staffordshire3.4
Gestamp West Midlands, Four Ashes Parkrooftop solarrooftop solar0.2approved, not builtupdated Jun 2026Mar 2026granted May 2026Jun 2026South Staffordshire3.5
Latherford Close, Four Ashes - Micro Energy Storagebattery storagebattery storage0.2approved, not builtupdated Mar 2025Oct 2024granted Feb 2025Mar 2025South Staffordshire4.2
Pillaton Foods, Cannock Roadrooftop solarrooftop solar0.7approved, not builtupdated Apr 2024Feb 2024granted Apr 2024Apr 2024South Staffordshire4.2
Four Ashes, Deepmore Lane Solar Farmbattery storagebattery storage—approved, not builtupdated Aug 2024Oct 2023granted Jul 2024Aug 2024South Staffordshire4.3
Acton Trussellrooftop solarrooftop solar0.9approved, not builtupdated Jun 2022May 2022granted Jul 2022Jun 2022South Staffordshire7.3
Finning Limited, Watling Street Solar Farmsolar farmsolar farm—application submitted may be out of dateupdated Aug 2023Jul 2023—Aug 2023Cannock Chase8.0
Energyst Rental Solutions, Station Road - Micro Energy Storage Facilitybattery storagebattery storage0.2approved, not builtupdated Jul 2025Apr 2025granted Jul 2025Jul 2025South Staffordshire8.2
I54 Project Trentrooftop solarrooftop solar0.3approved, not builtupdated Oct 2023Sep 2023granted Oct 2023Oct 2023South Staffordshire8.3
Innovation Drive, Bilbrook - Micro Energy Storage Projectbattery storagebattery storage0.2approved, not builtupdated Mar 2026Oct 2025granted Jan 2026Mar 2026South Staffordshire8.5
Valiant Way, Pendefordrooftop solarrooftop solar0.9approved, not builtupdated Mar 2023Feb 2023granted Mar 2023Mar 2023South Staffordshire8.5
Element Court, Hilton Cross Business Park - Micro Energy Storage Facilitybattery storagebattery storage0.2approved, not builtupdated Mar 2025Oct 2024granted Feb 2025Mar 2025South Staffordshire8.7
Stafford Manor High School, Rising Brookrooftop solarrooftop solar0.1approved, not builtupdated Dec 2025Oct 2025granted Nov 2025Dec 2025Stafford8.8
Balliol Business Park, Balliol Roadsolar farmsolar farm0.2approved, not builtupdated Mar 2024Nov 2023granted Mar 2024Mar 2024South Staffordshire9.4
Ormiston New Academy, Marsh Lanerooftop solarrooftop solar0.4approved, not builtupdated May 2026Jan 2026granted Feb 2026May 2026Wolverhampton9.6
Great Wyrley Performing Arts High Schoolrooftop solarrooftop solar0.2application withdrawnupdated Sep 2021Feb 2021—Sep 2021South Staffordshire9.9

Distance from the average position of the ST19 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm91620201
Rooftop solar1008104.7
Wind farm200110
Battery storage110901211

MW in pipeline: pending, approved and under-construction capacity.

How South Staffordshire decides solar, wind and battery applications

ApplicationsSouth StaffordshireUK
Decided applications (solar, wind, battery)4310,236
Refused7 (16%)19%
Solar refused1 of 1712%
Onshore wind refused2 of 345%
Battery storage refused4 of 2316%
Median time from submission to decision22.9 weeks17.0 weeks
Appeals lodged / allowed2 / 3—

All projects in South Staffordshire

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near ST19, 3 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.