Solar, wind and battery projects near Walsall (WS6)
55 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of WS6 (South Staffordshire): 6 are waiting for a planning decision, 36 approved but not yet running, 6 operational. The largest live scheme is Lions Den, Hammerwich (100 MW battery storage, approved on 24 July 2025, not yet built), 8.5 km away. Source: Renewable Energy Planning Database, July 2026 extract.
Projects within 10 km of WS6
Projects of 1 MW and more (20)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Hobble Lane, Great Wyrleybattery storage | battery storage | 49.9 | approved, not builtupdated May 2026 | Jan 2024 | granted Feb 2025 | May 2026 | South Staffordshire | 1.9 |
| Lime Lane, Pelsallbattery storage | battery storage | 100 | refusedupdated Jun 2026 | Jul 2025 | refused May 2026 | Jun 2026 | Cannock Chase | 3.3 |
| Bognop Road, Essington Solar Farm & Battery Energy Storagesolar farm | solar farm | 35 | application submittedupdated Dec 2024 | Nov 2024 | — | Dec 2024 | South Staffordshire | 3.9 |
| Upper Latherford Farm, Latherford Lanebattery storage | battery storage | 50 | approved, not builtupdated Nov 2024 | Nov 2023 | granted Oct 2024 | Nov 2024 | South Staffordshire | 4.9 |
| New Road, Featherstonebattery storage | battery storage | 100 | application withdrawnupdated Jul 2025 | Dec 2023 | — | Jul 2025 | South Staffordshire | 4.9 |
| Oaklands Farm, New Roadbattery storage | battery storage | 70 | approved, not built may be out of dateupdated Sep 2024 | Dec 2023 | granted Aug 2024 | Sep 2024 | South Staffordshire | 5.6 |
| Bleak Housewind farm | wind farm | 6.5 | application withdrawnupdated Aug 2010 | Jan 2008 | — | Aug 2010 | Cannock Chase | 5.9 |
| Four Ashes, Deepmore Lane Solar Farmsolar farm | solar farm | 22.5 | approved, not builtupdated Aug 2024 | Oct 2023 | granted Jul 2024 | Aug 2024 | South Staffordshire | 6.9 |
| Barr Farmsolar farm | solar farm | 1.8 | operationalupdated Apr 2015 | Jun 2014 | granted Aug 2014 | Apr 2015 | South Staffordshire | 7.1 |
| Bloxwich Batterybattery storage | battery storage | 41 | operationalupdated Sep 2020 | Sep 2016 | granted Feb 2022 | Sep 2020 | Walsall | 7.7 |
| Lawn Lane, Coven Solar Farmsolar farm | solar farm | 48 | approved, not builtupdated Feb 2026 | Dec 2023 | granted Aug 2024 | Feb 2026 | South Staffordshire | 8.0 |
| Rodbastonwind farm | wind farm | 4 | operationalupdated Apr 2017 | Jul 2009 | granted Dec 2010 | Apr 2017 | South Staffordshire | 8.0 |
| Land East of Lawn Lanesolar farm | solar farm | 5 | operationalupdated Aug 2016 | Aug 2015 | granted Nov 2015 | Aug 2016 | South Staffordshire | 8.3 |
| Valiant Way, Pendefordrooftop solar | rooftop solar | 1.2 | approved, not built may be out of dateupdated Dec 2021 | Aug 2021 | granted Nov 2021 | Dec 2021 | South Staffordshire | 8.3 |
| College Farmsolar farm | solar farm | 4.8 | refused on appealupdated Feb 2017 | May 2015 | refused Nov 2015 | Feb 2017 | Walsall | 8.3 |
| Tesco Superstore Wisemorerooftop solar | rooftop solar | 1 | approved, not builtupdated Mar 2020 | Mar 2020 | granted Jul 2020 | Mar 2020 | Walsall | 8.4 |
| Jaguar Land Roverrooftop solar | rooftop solar | 5.8 | operationalupdated Dec 2014 | May 2014 | granted Aug 2014 | Dec 2014 | South Staffordshire | 8.4 |
| Lions Den, Hammerwichbattery storage | battery storage | 100 | approved, not builtupdated Aug 2025 | Dec 2024 | granted Jul 2025 | Aug 2025 | Lichfield | 8.5 |
| EPSRC Willenhallbattery storage | battery storage | 2 | operationalupdated Oct 2018 | — | — | Oct 2018 | Walsall | 8.5 |
| Bowmans Harbour Solar Farmsolar farm | solar farm | 6.9 | under constructionupdated Feb 2022 | Nov 2020 | granted Apr 2022 | Feb 2022 | Wolverhampton | 8.8 |
Smaller schemes under 1 MW, mostly rooftop solar (35)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Great Wyrley Performing Arts High Schoolrooftop solar | rooftop solar | 0.2 | application withdrawnupdated Sep 2021 | Feb 2021 | — | Sep 2021 | South Staffordshire | 0.8 |
| Finning Limited, Watling Street Solar Farmsolar farm | solar farm | — | application submitted may be out of dateupdated Aug 2023 | Jul 2023 | — | Aug 2023 | Cannock Chase | 2.3 |
| Bognop Road, Essington Solar Farm & Battery Energy Storagebattery storage | battery storage | — | application submittedupdated Dec 2024 | Nov 2024 | — | Dec 2024 | South Staffordshire | 3.9 |
| Energyst Rental Solutions, Station Road - Micro Energy Storage Facilitybattery storage | battery storage | 0.2 | approved, not builtupdated Jul 2025 | Apr 2025 | granted Jul 2025 | Jul 2025 | South Staffordshire | 4.7 |
| Element Court, Hilton Cross Business Park - Micro Energy Storage Facilitybattery storage | battery storage | 0.2 | approved, not builtupdated Mar 2025 | Oct 2024 | granted Feb 2025 | Mar 2025 | South Staffordshire | 5.3 |
| AC Steels, Fryers Roadrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Jan 2025 | Oct 2024 | granted Dec 2024 | Jan 2025 | Walsall | 5.7 |
| Steel Processing Midlands, Burntwood Business Parkrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Mar 2024 | Jan 2024 | granted Mar 2024 | Mar 2024 | Lichfield | 6.1 |
| Willenhall E Act School Academy, Furzebank Wayrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Sep 2023 | Jul 2023 | granted Aug 2023 | Sep 2023 | Walsall | 6.7 |
| Four Ashes, Deepmore Lane Solar Farmbattery storage | battery storage | — | approved, not builtupdated Aug 2024 | Oct 2023 | granted Jul 2024 | Aug 2024 | South Staffordshire | 6.9 |
| Latherford Close, Four Ashes - Micro Energy Storagebattery storage | battery storage | 0.2 | approved, not builtupdated Mar 2025 | Oct 2024 | granted Feb 2025 | Mar 2025 | South Staffordshire | 7.0 |
| Six Towers Roadbattery storage | battery storage | — | refusedupdated Jul 2025 | Aug 2024 | refused May 2025 | Jul 2025 | Walsall | 7.1 |
| Gestamp West Midlands, Four Ashes Parkrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Jun 2026 | Mar 2026 | granted May 2026 | Jun 2026 | South Staffordshire | 7.2 |
| The Food Warehouse, Reedswood Wayrooftop solar | rooftop solar | 0.1 | approved, not builtupdated Jan 2026 | Oct 2025 | granted Dec 2025 | Jan 2026 | Walsall | 7.2 |
| Pillaton Foods, Cannock Roadrooftop solar | rooftop solar | 0.7 | approved, not builtupdated Apr 2024 | Feb 2024 | granted Apr 2024 | Apr 2024 | South Staffordshire | 7.7 |
| Arnold Clark, Bearing Driverooftop solar | rooftop solar | 0.4 | approved, not builtupdated Dec 2024 | Apr 2024 | granted Apr 2024 | Dec 2024 | Wolverhampton | 7.9 |
| I54 Project Trentrooftop solar | rooftop solar | 0.3 | approved, not builtupdated Oct 2023 | Sep 2023 | granted Oct 2023 | Oct 2023 | South Staffordshire | 8.2 |
| Middlemore Lane West, Aldridgerooftop solar | rooftop solar | 0.2 | approved, not builtupdated Mar 2022 | Feb 2022 | granted Mar 2022 | Mar 2022 | Walsall | 8.3 |
| Innovation Drive, Bilbrook - Micro Energy Storage Projectbattery storage | battery storage | 0.2 | approved, not builtupdated Mar 2026 | Oct 2025 | granted Jan 2026 | Mar 2026 | South Staffordshire | 8.3 |
| Valiant Way, Pendefordrooftop solar | rooftop solar | 0.9 | approved, not builtupdated Mar 2023 | Feb 2023 | granted Mar 2023 | Mar 2023 | South Staffordshire | 8.3 |
| West Walsall E Act Academy, Primley Avenuerooftop solar | rooftop solar | 0.2 | approved, not builtupdated Nov 2023 | Sep 2023 | granted Oct 2023 | Nov 2023 | Walsall | 8.6 |
| Morrison Supermarkets, Lichfield Streetrooftop solar | rooftop solar | 0.2 | approved, not built may be out of dateupdated Dec 2022 | Oct 2022 | granted Dec 2022 | Dec 2022 | Walsall | 8.6 |
| Manor Hospital, Moat Roadrooftop solar | rooftop solar | 0.4 | approved, not builtupdated May 2026 | Jan 2026 | granted Mar 2026 | May 2026 | Walsall | 8.6 |
| Assa Abloy The Meadows, Cannock Roadrooftop solar | rooftop solar | — | approved, not builtupdated Jun 2023 | Apr 2023 | granted May 2023 | Jun 2023 | Wolverhampton | 8.7 |
| Scanmetals Limited, Bilston Lanerooftop solar | rooftop solar | 0.5 | approved, not built may be out of dateupdated May 2023 | Apr 2023 | granted May 2023 | May 2023 | Walsall | 8.7 |
| Middleton Paper Company, Portobello Worksrooftop solar | rooftop solar | 0.5 | approved, not builtupdated May 2026 | Jan 2026 | granted Feb 2026 | May 2026 | Walsall | 8.8 |
| Rakegate Primary Schoolrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Dec 2025 | Oct 2025 | granted Nov 2025 | Dec 2025 | Wolverhampton | 8.8 |
| Ormiston New Academy, Marsh Lanerooftop solar | rooftop solar | 0.4 | approved, not builtupdated May 2026 | Jan 2026 | granted Feb 2026 | May 2026 | Wolverhampton | 8.8 |
| Jerome Retail Park, Midland Roadrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Nov 2023 | Sep 2023 | granted Oct 2023 | Nov 2023 | Walsall | 8.9 |
| Saxon Road - Micro Energy Storage Facilitybattery storage | battery storage | 0.2 | refusedupdated Sep 2025 | Mar 2025 | refused Sep 2025 | Sep 2025 | South Staffordshire | 8.9 |
| Sherwood House, Showell Roadrooftop solar | rooftop solar | 0.3 | application submittedupdated Oct 2025 | Sep 2025 | — | Oct 2025 | Wolverhampton | 9.1 |
| Sherwood Stainless Steel, Mammoth Driverooftop solar | rooftop solar | 0.7 | approved, not builtupdated Sep 2023 | Jul 2023 | granted Aug 2023 | Sep 2023 | Wolverhampton | 9.1 |
| Brindley Honda, West Streetrooftop solar | rooftop solar | 0.2 | application submitted may be out of dateupdated Jul 2024 | Jun 2024 | — | Jul 2024 | Wolverhampton | 9.9 |
| University Technical College, Cambridge Streetrooftop solar | rooftop solar | — | approved, not builtupdated Aug 2023 | Jun 2023 | granted Aug 2023 | Aug 2023 | Wolverhampton | 9.9 |
| Erdington Road, Aldridgerooftop solar | rooftop solar | 0.3 | approved, not builtupdated May 2022 | Apr 2022 | granted May 2022 | May 2022 | Walsall | 9.9 |
| Cat & Kittens Lane, Slade Heath Solar Photovoltaics Panelsrooftop solar | rooftop solar | 0.2 | application submitted may be out of dateupdated Jul 2022 | Jun 2022 | — | Jul 2022 | Wolverhampton | 10.0 |
Distance from the average position of the WS6 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.
By type
| Type | All | Pending | Approved | Operational | Refused | MW in pipeline |
|---|---|---|---|---|---|---|
| Solar farm | 8 | 2 | 3 | 2 | 1 | 112 |
| Rooftop solar | 29 | 3 | 24 | 1 | 0 | 9.9 |
| Wind farm | 2 | 0 | 0 | 1 | 0 | 0 |
| Battery storage | 16 | 1 | 9 | 2 | 3 | 271 |
MW in pipeline: pending, approved and under-construction capacity.
How South Staffordshire decides solar, wind and battery applications
| Applications | South Staffordshire | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 43 | 10,236 |
| Refused | 7 (16%) | 19% |
| Solar refused | 1 of 17 | 12% |
| Onshore wind refused | 2 of 3 | 45% |
| Battery storage refused | 4 of 23 | 16% |
| Median time from submission to decision | 22.9 weeks | 17.0 weeks |
| Appeals lodged / allowed | 2 / 3 | — |
All projects in South Staffordshire
Is the status up to date?
32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near WS6, 7 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.