Land East of Lawn Lane (5 MW solar farm)

Land East of Lawn Lane is a 5 MW solar farm project in South Staffordshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 30 March 2016; the record was last updated on 18 August 2016.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

5 MWsolar farm
operationalstatus in REPD
18 August 2016record last updated
South Staffordshirecouncil area

Planning timeline

DateStage
13 August 2015Application submitted
12 November 2015Planning permission granted
15 February 2016Construction started
30 March 2016Operational

Project details

Technology
solar farm
Capacity
5 MW
Status (REPD)
operational
Record last updated
18 August 2016
Operator or applicant
Lightsource Renewable Energy
Planning authority
South Staffordshire
Planning application reference
15/00648/FUL
Address (REPD)
Land East Of, Lawn Lane, Coven, Wolverhampton
Council area (by location)
South Staffordshire
Time to decision
13 weeks
REPD reference
5568

Who decides

ApplicationsSouth StaffordshireUK
Decided applications (solar, wind, battery)4310,236
Refused7 (16%)19%
Solar refused1 of 1712%
Onshore wind refused2 of 345%
Battery storage refused4 of 2316%
Median time from submission to decision22.9 weeks17.0 weeks
Appeals lodged / allowed2 / 3—

Other large projects within 10 km

ProjectTypeMWStatuskm
Jaguar Land Roverrooftop solar5.8operational0.8
Lawn Lane, Coven Solar Farmsolar farm48approved, not built1.0
Oaklands Farm, New Roadbattery storage70approved, not built2.8
New Road, Featherstonebattery storage100application withdrawn3.4
Four Ashes, Deepmore Lane Solar Farmsolar farm22.5approved, not built3.9
Upper Latherford Farm, Latherford Lanebattery storage50approved, not built4.3
Chillington Estate, Chillington Parksolar farm40approved, not built4.6
Bognop Road, Essington Solar Farm & Battery Energy Storagesolar farm35application submitted5.6
Bowmans Harbour Solar Farmsolar farm6.9under construction6.2

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.6405, -2.1418).