Lawn Lane, Coven Solar Farm (48 MW)

Lawn Lane, Coven Solar Farm is a 48 MW solar farm project in South Staffordshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 22 August 2024, not yet built; the record was last updated on 16 February 2026.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

48 MWsolar farm
approved, not builtstatus in REPD
16 February 2026record last updated
South Staffordshirecouncil area

Planning timeline

DateStage
27 December 2023Application submitted
22 August 2024Planning permission granted
22 August 2027Permission due to expire (unless work starts)

Project details

Technology
solar farm
Capacity
48 MW
Status (REPD)
approved, not built
Record last updated
16 February 2026
Operator or applicant
Anesco Limited
Planning authority
South Staffordshire
Planning application reference
23/01083/FULM
Site area
58.0 ha
Address (REPD)
Lawn Lane, Coven, Wolverhampton
Council area (by location)
South Staffordshire
Time to decision
34 weeks
Contracts for Difference
AR7a
Name in REPD
Lawn Lane, Coven - Solar Farm
REPD reference
14574

Who decides

ApplicationsSouth StaffordshireUK
Decided applications (solar, wind, battery)4310,236
Refused7 (16%)19%
Solar refused1 of 1712%
Onshore wind refused2 of 345%
Battery storage refused4 of 2316%
Median time from submission to decision22.9 weeks17.0 weeks
Appeals lodged / allowed2 / 3—

Other large projects within 10 km

ProjectTypeMWStatuskm
Land East of Lawn Lanesolar farm5operational1.0
Jaguar Land Roverrooftop solar5.8operational1.8
Oaklands Farm, New Roadbattery storage70approved, not built2.3
Four Ashes, Deepmore Lane Solar Farmsolar farm22.5approved, not built3.0
New Road, Featherstonebattery storage100application withdrawn3.2
Upper Latherford Farm, Latherford Lanebattery storage50approved, not built3.6
Chillington Estate, Chillington Parksolar farm40approved, not built4.4
Bognop Road, Essington Solar Farm & Battery Energy Storagesolar farm35application submitted5.8
Bowmans Harbour Solar Farmsolar farm6.9under construction7.1

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.6492, -2.1403).