Chillington Estate, Chillington Park (40 MW solar farm)

Chillington Estate, Chillington Park is a 40 MW solar farm project in South Staffordshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 25 July 2025, not yet built; the record was last updated on 16 February 2026.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

40 MWsolar farm
approved, not builtstatus in REPD
16 February 2026record last updated
South Staffordshirecouncil area

Planning timeline

DateStage
17 November 2023Application submitted
25 July 2025Planning permission granted
25 July 2028Permission due to expire (unless work starts)

Project details

Technology
solar farm
Capacity
40 MW
Status (REPD)
approved, not built
Record last updated
16 February 2026
Operator or applicant
Elgin Energy Esco Limited
Planning authority
South Staffordshire
Planning application reference
23/00576/FULM
Site area
65.0 ha
Address (REPD)
Chillington Estate Chillington Park Chillington
Council area (by location)
South Staffordshire
Time to decision
88 weeks
Contracts for Difference
AR7a
Name in REPD
Chillington Estate, Chillington Park - Solar Panels
REPD reference
14087

The scheme also includes 40 MW of battery storage, recorded separately in REPD (approved, not built).

Who decides

ApplicationsSouth StaffordshireUK
Decided applications (solar, wind, battery)4310,236
Refused7 (16%)19%
Solar refused1 of 1712%
Onshore wind refused2 of 345%
Battery storage refused4 of 2316%
Median time from submission to decision22.9 weeks17.0 weeks
Appeals lodged / allowed2 / 3—

Other large projects within 10 km

ProjectTypeMWStatuskm
Albrighton Substation, Beamish Lanebattery storage7approved, not built3.6
Albrighton Solar farmsolar farm15.8operational3.8
County Lane Solar farmsolar farm16approved, not built3.9
Lawn Lane, Coven Solar Farmsolar farm48approved, not built4.4
Land East of Lawn Lanesolar farm5operational4.6
Jaguar Land Roverrooftop solar5.8operational5.1
Four Ashes, Deepmore Lane Solar Farmsolar farm22.5approved, not built5.7
Solar Farm & Battery Storage at The South Of Holyhead Road Albrightonsolar farm23operational6.5
Oaklands Farm, New Roadbattery storage70approved, not built6.6

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.6587, -2.2034).