Energy Projects Near You

Albrighton Substation, Beamish Lane (7 MW battery storage)

Albrighton Substation, Beamish Lane is a 7 MW battery storage project in Shropshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 26 February 2024, not yet built; the record was last updated on 4 March 2024.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

7 MWbattery storage
approved, not builtstatus in REPD
4 March 2024record last updated
Shropshirecouncil area

Planning timeline

DateStage
2 November 2023Application submitted
26 February 2024Planning permission granted
26 February 2027Permission due to expire (unless work starts)

Project details

Technology
battery storage (stand-alone storage)
Capacity
7 MW
Status (REPD)
approved, not built
Record last updated
4 March 2024
Operator or applicant
Fig Power (part of Hydrock)
Planning authority
Shropshire
Planning application reference
23/04541/FUL
Address (REPD)
North of Albrighton Substation, Beamish Lane, Albrighton
Council area (by location)
Shropshire
Time to decision
17 weeks
Name in REPD
Albrighton Substation, Beamish Lane - Battery Storage
REPD reference
15306

Earlier applications for this site

ApplicationMWSubmittedOutcome
Albrighton Substation, Beamish Lane 22/05043/FUL728 November 2022withdrawn 12 April 2023

Who decides

ApplicationsShropshireUK
Decided applications (solar, wind, battery)9810,236
Refused22 (22%)19%
Solar refused20 of 7812%
Onshore wind refused2 of 345%
Battery storage refused0 of 1716%
Median time from submission to decision15.2 weeks17.0 weeks
Appeals lodged / allowed10 / 5—

Other large projects within 10 km

ProjectTypeMWStatuskm
County Lane Solar farmsolar farm16approved, not built0.3
Albrighton Solar farmsolar farm15.8operational0.5
Solar Farm & Battery Storage at The South Of Holyhead Road Albrightonsolar farm23operational2.9
Chillington Estate, Chillington Parksolar farm40approved, not built3.6
Land East of Lawn Lanesolar farm5operational6.9
Jaguar Land Roverrooftop solar5.8operational7.0
Lawn Lane, Coven Solar Farmsolar farm48approved, not built7.1
Pool Hall Farm, Lower Pennbattery storage100approved, not built7.5
Wolverhampton West Sub Stationbattery storage50permission expired8.2

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.6373, -2.2438).