Solar, wind and battery projects near Wolverhampton (WV7)
31 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of WV7 (Shropshire): 1 is waiting for a planning decision, 21 approved but not yet running, 7 operational. The largest live scheme is Pool Hall Farm, Lower Penn (100 MW battery storage, approved on 21 July 2025, not yet built), 8.4 km away. Source: Renewable Energy Planning Database, July 2026 extract.
Projects within 10 km of WV7
Projects of 1 MW and more (20)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Albrighton Solar farmsolar farm | solar farm | 15.8 | operationalupdated May 2017 | Jul 2015 | granted Dec 2015 | May 2017 | Shropshire | 2.0 |
| Solar Farm & Battery Storage at The South Of Holyhead Road Albrightonsolar farm | solar farm | 23 | operationalupdated Jun 2025 | Jul 2022 | granted Jun 2023 | Jun 2025 | Shropshire | 2.1 |
| Country Lane Solar Developmentsolar farm | solar farm | 4.7 | application withdrawnupdated Jul 2017 | Oct 2015 | — | Jul 2017 | Shropshire | 2.1 |
| County Lane Solar farmsolar farm | solar farm | 16 | approved, not built may be out of dateupdated Feb 2026 | Apr 2022 | granted Mar 2023 | Feb 2026 | Shropshire | 2.3 |
| Albrighton Substation, Beamish Lanebattery storage | battery storage | 7 | approved, not builtupdated Mar 2024 | Nov 2023 | granted Feb 2024 | Mar 2024 | Shropshire | 2.4 |
| Chillington Estate, Chillington Parksolar farm | solar farm | 40 | approved, not builtupdated Feb 2026 | Nov 2023 | granted Jul 2025 | Feb 2026 | South Staffordshire | 5.7 |
| Chillington Estate, Chillington Parkbattery storage | battery storage | 40 | approved, not builtupdated Feb 2026 | Nov 2023 | granted Jul 2025 | Feb 2026 | South Staffordshire | 5.7 |
| Pool Hall Farm, Lower Pennbattery storage | battery storage | 100 | approved, not builtupdated Sep 2025 | Jan 2025 | granted Jul 2025 | Sep 2025 | South Staffordshire | 8.4 |
| Kemberton Solar Farmsolar farm | solar farm | 22 | approved, not builtupdated Mar 2024 | Jun 2022 | granted Feb 2024 | Mar 2024 | Shropshire | 8.5 |
| Land East of Lawn Lanesolar farm | solar farm | 5 | operationalupdated Aug 2016 | Aug 2015 | granted Nov 2015 | Aug 2016 | South Staffordshire | 9.3 |
| Ebstree Road, Trysull, Seisdonbattery storage | battery storage | 99.9 | approved, not builtupdated Jan 2026 | May 2025 | granted Nov 2025 | Jan 2026 | South Staffordshire | 9.3 |
| Ebstree Road, Trysullbattery storage | battery storage | 49.9 | approved, not builtupdated Jan 2025 | Dec 2023 | granted Nov 2024 | Jan 2025 | South Staffordshire | 9.3 |
| Jaguar Land Roverrooftop solar | rooftop solar | 5.8 | operationalupdated Dec 2014 | May 2014 | granted Aug 2014 | Dec 2014 | South Staffordshire | 9.3 |
| South Staffordshire Railway Walk, Castlecroftbattery storage | battery storage | 50 | approved, not built may be out of dateupdated Aug 2022 | May 2021 | granted Aug 2022 | Aug 2022 | South Staffordshire | 9.4 |
| Wolverhampton West Sub Stationbattery storage | battery storage | 50 | permission expiredupdated Aug 2020 | Aug 2016 | granted Oct 2016 | Aug 2020 | Wolverhampton | 9.4 |
| Lawn Lane, Coven Solar Farmsolar farm | solar farm | 48 | approved, not builtupdated Feb 2026 | Dec 2023 | granted Aug 2024 | Feb 2026 | South Staffordshire | 9.5 |
| Valiant Way, Pendefordrooftop solar | rooftop solar | 1.2 | approved, not built may be out of dateupdated Dec 2021 | Aug 2021 | granted Nov 2021 | Dec 2021 | South Staffordshire | 9.5 |
| Penstone Lane, Penn 1battery storage | battery storage | 50 | approved, not built may be out of dateupdated Mar 2022 | Feb 2022 | granted Sep 2022 | Mar 2022 | South Staffordshire | 9.7 |
| Penstone Lane, Lower Penn 2battery storage | battery storage | 50 | approved, not built may be out of dateupdated Mar 2022 | Feb 2022 | granted Sep 2022 | Mar 2022 | South Staffordshire | 9.7 |
| Sheriffhales Solar Farmsolar farm | solar farm | 8.2 | operationalupdated Aug 2016 | Mar 2015 | granted Jul 2015 | Aug 2016 | Shropshire | 10.0 |
Smaller schemes under 1 MW, mostly rooftop solar (11)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Albrighton Solar farmbattery storage | battery storage | — | operationalupdated Feb 2019 | Dec 2015 | granted Dec 2015 | Feb 2019 | Shropshire | 2.0 |
| Solar Farm & Battery Storage at The South Of Holyhead Road Albrightonbattery storage | battery storage | — | operationalupdated Jun 2025 | Jul 2022 | granted Jun 2023 | Jun 2025 | Shropshire | 2.1 |
| County Lane Solar farmbattery storage | battery storage | — | approved, not built may be out of dateupdated Feb 2026 | Apr 2022 | granted Mar 2023 | Feb 2026 | Shropshire | 2.3 |
| Balliol Business Park, Balliol Roadsolar farm | solar farm | 0.2 | approved, not builtupdated Mar 2024 | Nov 2023 | granted Mar 2024 | Mar 2024 | South Staffordshire | 7.9 |
| Bridgnorth Garden Centre - Storage Warehouserooftop solar | rooftop solar | — | approved, not built may be out of dateupdated Apr 2023 | Sep 2022 | granted Mar 2023 | Apr 2023 | South Staffordshire | 8.1 |
| Innovation Drive, Bilbrook - Micro Energy Storage Projectbattery storage | battery storage | 0.2 | approved, not builtupdated Mar 2026 | Oct 2025 | granted Jan 2026 | Mar 2026 | South Staffordshire | 9.5 |
| Valiant Way, Pendefordrooftop solar | rooftop solar | 0.9 | approved, not builtupdated Mar 2023 | Feb 2023 | granted Mar 2023 | Mar 2023 | South Staffordshire | 9.5 |
| I54 Project Trentrooftop solar | rooftop solar | 0.3 | approved, not builtupdated Oct 2023 | Sep 2023 | granted Oct 2023 | Oct 2023 | South Staffordshire | 9.5 |
| Ormiston New Academy, Marsh Lanerooftop solar | rooftop solar | 0.4 | approved, not builtupdated May 2026 | Jan 2026 | granted Feb 2026 | May 2026 | Wolverhampton | 9.5 |
| Mail Solutionsrooftop solar | rooftop solar | 0.6 | application submitted may be out of dateupdated Jun 2024 | May 2024 | — | Jun 2024 | Telford and Wrekin | 9.7 |
| Rakegate Primary Schoolrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Dec 2025 | Oct 2025 | granted Nov 2025 | Dec 2025 | Wolverhampton | 9.8 |
Distance from the average position of the WV7 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.
By type
| Type | All | Pending | Approved | Operational | Refused | MW in pipeline |
|---|---|---|---|---|---|---|
| Solar farm | 10 | 0 | 5 | 4 | 0 | 126 |
| Rooftop solar | 8 | 1 | 6 | 1 | 0 | 3.6 |
| Battery storage | 13 | 0 | 10 | 2 | 0 | 447 |
MW in pipeline: pending, approved and under-construction capacity.
How Shropshire decides solar, wind and battery applications
| Applications | Shropshire | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 98 | 10,236 |
| Refused | 22 (22%) | 19% |
| Solar refused | 20 of 78 | 12% |
| Onshore wind refused | 2 of 3 | 45% |
| Battery storage refused | 0 of 17 | 16% |
| Median time from submission to decision | 15.2 weeks | 17.0 weeks |
| Appeals lodged / allowed | 10 / 5 | — |
Is the status up to date?
32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near WV7, 8 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.