Kemberton Solar Farm (22 MW)

Kemberton Solar Farm is a 22 MW solar farm project in Shropshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 22 February 2024, not yet built; the record was last updated on 1 March 2024.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

22 MWsolar farm
approved, not builtstatus in REPD
1 March 2024record last updated
Shropshirecouncil area

Planning timeline

DateStage
13 June 2022Application submitted
20 March 2023Refused by the planning authority
2 October 2023Appeal lodged
22 February 2024Planning permission granted
22 February 2024Appeal allowed
22 February 2027Permission due to expire (unless work starts)

Project details

Technology
solar farm
Capacity
22 MW
Status (REPD)
approved, not built
Record last updated
1 March 2024
Operator or applicant
Vattenfall
Planning authority
Shropshire
Planning application reference
22/02441/FUL
Appeal reference
23/03189/REF
Site area
19.9 ha
Address (REPD)
The S/O Hall Lane, Kemberton, Shifnal
Council area (by location)
Shropshire
Time to decision
88 weeks
Contracts for Difference
AR6
Name in REPD
Kemberton - Solar Farm
REPD reference
11202

Who decides

ApplicationsShropshireUK
Decided applications (solar, wind, battery)9810,236
Refused22 (22%)19%
Solar refused20 of 7812%
Onshore wind refused2 of 345%
Battery storage refused0 of 1716%
Median time from submission to decision15.2 weeks17.0 weeks
Appeals lodged / allowed10 / 5—

Other large projects within 10 km

ProjectTypeMWStatuskm
Hollydale, Buildwas Roadbattery storage40approved, not built7.7
Buildwasbattery storage100approved, not built7.7
Granville Road Solar Farmsolar farm5operational8.0
Sheriffhales Solar Farmsolar farm8.2operational8.1
New Works Lane Solar Farmsolar farm30application submitted8.5
Steeraway Farm Solar Farmsolar farm30under construction8.8
Solar Farm & Battery Storage at The South Of Holyhead Road Albrightonsolar farm23operational9.2

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.6376, -2.4043).