Energy Projects Near You

Sheriffhales Solar Farm (8.2 MW)

Sheriffhales Solar Farm is an 8.2 MW solar farm project in Shropshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 16 December 2015; the record was last updated on 18 August 2016.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

8.2 MWsolar farm
operationalstatus in REPD
18 August 2016record last updated
Shropshirecouncil area

Planning timeline

DateStage
27 March 2015Application submitted
1 July 2015Planning permission granted
1 October 2015Construction started
16 December 2015Operational

Project details

Technology
solar farm
Capacity
8.2 MW
Status (REPD)
operational
Record last updated
18 August 2016
Operator or applicant
Lightsource Renewable Energy
Planning authority
Shropshire
Planning application reference
15/01366/FUL
Site area
17.6 ha
Address (REPD)
Land west of Sheriffhales, 16 Sandy Lane, Sheriffhales, Shifnal,
Council area (by location)
Shropshire
Time to decision
14 weeks
REPD reference
5169

Earlier applications for this site

ApplicationMWSubmittedOutcome
Sheriffhales Solar Farm 14/03444/FUL30.51 August 2014refused 10 December 2014

Who decides

ApplicationsShropshireUK
Decided applications (solar, wind, battery)9810,236
Refused22 (22%)19%
Solar refused20 of 7812%
Onshore wind refused2 of 345%
Battery storage refused0 of 1716%
Median time from submission to decision15.2 weeks17.0 weeks
Appeals lodged / allowed10 / 5—

Other large projects within 10 km

ProjectTypeMWStatuskm
Granville Road Solar Farmsolar farm5operational2.9
Twitch Hill, Cheswell Grange Farm Solar Farm & Battery Storagesolar farm25under construction5.9
King's Streetwind farm12refused7.0
Kemberton Solar Farmsolar farm22approved, not built8.1
New Works Lane Solar Farmsolar farm30application submitted9.3
Steeraway Farm Solar Farmsolar farm30under construction9.9

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.7067, -2.3689).