Energy Projects Near You

New Works Lane Solar Farm (30 MW)

New Works Lane Solar Farm is a 30 MW solar farm project in Telford and Wrekin, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: application submitted on 23 July 2021, no decision recorded; the record was last updated on 4 August 2021. The application was submitted more than two years ago and is still shown as pending; it may have been decided since. Check the planning authority's register for the latest position.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

30 MWsolar farm
application submittedmay be out of datestatus in REPD
4 August 2021record last updated
Telford and Wrekincouncil area

The application was submitted more than two years ago and is still shown as pending; it may have been decided since. 32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided.

Planning timeline

DateStage
23 July 2021Application submitted

Project details

Technology
solar farm
Capacity
30 MW
Status (REPD)
application submitted
Record last updated
4 August 2021
Operator or applicant
Greentech
Planning authority
Telford and Wrekin
Planning application reference
TWC/2021/0737
Site area
39.0 ha
Address (REPD)
W/O New Works Lane, Lawley, Telford
Council area (by location)
Telford and Wrekin
Contracts for Difference
AR5
Name in REPD
New Works Lane - Solar Farm
REPD reference
9381

Who decides

ApplicationsTelford and WrekinUK
Decided applications (solar, wind, battery)3410,236
Refused6 (18%)19%
Solar refused1 of 2512%
Battery storage refused5 of 916%
Median time from submission to decision12.7 weeks17.0 weeks
Appeals lodged / allowed2 / 5—

Other large projects within 10 km

ProjectTypeMWStatuskm
Steeraway Farm Solar Farmsolar farm30under construction0.6
Tiddiecross Solar Farm & Battery Storagesolar farm14approved, not built5.3
Tiddiecross Solar Farmsolar farm10.5operational5.3
Hollydale, Buildwas Roadbattery storage40approved, not built5.4
Buildwasbattery storage100approved, not built5.4
Rushmoor Lane Farm (Cheshire Coppice)solar farm5operational5.7
Granville Road Solar Farmsolar farm5operational6.6
Twitch Hill, Cheswell Grange Farm Solar Farm & Battery Storagesolar farm25under construction8.4
Kemberton Solar Farmsolar farm22approved, not built8.5

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.6855, -2.5026).