Renewable energy projects in Telford and Wrekin

42 solar, wind or battery projects of 150 kW or more are located in Telford and Wrekin (REPD, July 2026 extract): 3 pending, 28 approved but not running, 6 operational and 1 refused. The council refused 6 of 34 decided applications (18%; UK 19%), with a median 13 weeks from submission to decision.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

42projects in the council area
3awaiting a decision
28approved, not running
18%of decisions refused

How Telford and Wrekin decides

ApplicationsTelford and WrekinUK
Decided applications (solar, wind, battery)3410,236
Refused6 (18%)19%
Solar refused1 of 2512%
Battery storage refused5 of 916%
Median time from submission to decision12.7 weeks17.0 weeks
Appeals lodged / allowed2 / 5—

Projects in Telford and Wrekin

Projects of 1 MW and more (15)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updated
Myttons Solar Farmsolar farmsolar farm49.9approved, not built may be out of dateupdated Jan 2021Oct 2020granted Mar 2021Jan 2021
High Ercall Solar Farmsolar farmsolar farm49.9approved, not builtupdated Sep 2023Jan 2023granted Aug 2023Sep 2023
New Works Lane Solar Farmsolar farmsolar farm30application submitted may be out of dateupdated Aug 2021Jul 2021—Aug 2021
Steeraway Farm Solar Farmsolar farmsolar farm30under constructionupdated Jan 2026Oct 2021granted May 2023Jan 2026
Twitch Hill, Cheswell Grange Farm Solar Farm & Battery Storagesolar farmsolar farm25under constructionupdated Jul 2024Dec 2021granted Jun 2022Jul 2024
Tiddiecross Solar Farm & Battery Storagesolar farmsolar farm14approved, not builtupdated Feb 2026Dec 2024granted Jun 2025Feb 2026
Tiddiecross Solar Farmsolar farmsolar farm10.5operationalupdated May 2016Sep 2014granted Jan 2015May 2016
Rushmoor Lane Farm (Cheshire Coppice)solar farmsolar farm5operationalupdated Feb 2016Jun 2015granted Oct 2015Feb 2016
Granville Road Solar Farmsolar farmsolar farm5operationalupdated Feb 2017Sep 2015granted Dec 2015Feb 2017
Wheat Leasows Solar Parksolar farmsolar farm4operationalupdated Jan 2016Feb 2014granted May 2014Jan 2016
Lyreco - Telford Distribution Centrerooftop solarrooftop solar3.8operationalupdated Jan 2016——Jan 2016
Lyreco, Donnington Woodrooftop solarrooftop solar3.8approved, not builtupdated Mar 2026Nov 2025granted Dec 2025Mar 2026
Princess Royal Hospital, Grainger Driverooftop solarrooftop solar2.1approved, not builtupdated Jun 2026Apr 2026granted Jun 2026Jun 2026
Telford Shopping Centre Solar Photovoltaic PV Arraysolar farmsolar farm1.8approved, not built may be out of dateupdated Feb 2022Nov 2021granted Jan 2022Feb 2022
Ricoh UK Productssolar farmsolar farm1.2operationalupdated Mar 2020Mar 2020granted Aug 2020Mar 2020
Smaller schemes under 1 MW, mostly rooftop solar (27)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updated
Greenhous Village, Osbastonrooftop solarrooftop solar0.8approved, not builtupdated Jan 2023Sep 2022granted Nov 2022Jan 2023
Kraft Heinz, Hortonwoodrooftop solarrooftop solar0.8approved, not builtupdated Jun 2026Mar 2026granted Apr 2026Jun 2026
Telford Shopping Centre, Woodhouse Centralrooftop solarrooftop solar0.7approved, not builtupdated Oct 2023Aug 2023granted Sep 2023Oct 2023
Mail Solutionsrooftop solarrooftop solar0.6application submitted may be out of dateupdated Jun 2024May 2024—Jun 2024
Telford Shopping Centre, Northfield Streetrooftop solarrooftop solar0.6approved, not builtupdated May 2026Feb 2026granted Mar 2026May 2026
TCL Packaging, Stafford Parkrooftop solarrooftop solar0.5approved, not builtupdated Jul 2025Apr 2025granted Apr 2025Jul 2025
Wz Packaging, Halesfieldrooftop solarrooftop solar0.5approved, not builtupdated Jul 2022Jul 2022granted Jul 2022Jul 2022
Sugden Farmrooftop solarrooftop solar0.4approved, not builtupdated Aug 2023May 2023granted Aug 2023Aug 2023
Makita Manufacturing Europerooftop solarrooftop solar0.4approved, not builtupdated Jun 2022Jun 2022granted Jul 2022Jun 2022
Parkside Court Solar Panels & Air Source Heat Pumpsrooftop solarrooftop solar0.3approved, not built may be out of dateupdated Jul 2022Jun 2022granted Aug 2022Jul 2022
Furrows Ford Store, Furrows Business Parkrooftop solarrooftop solar0.3approved, not builtupdated Oct 2024Aug 2024granted Sep 2024Oct 2024
Telford Ten Pin, International Wayrooftop solarrooftop solar0.2approved, not builtupdated Nov 2023Sep 2023granted Oct 2023Nov 2023
Duce Drive, Dawley Energy Storage Facilitybattery storagebattery storage0.2application withdrawnupdated Feb 2025Nov 2024—Feb 2025
Oakengates Leisure Centre, New Road - Micro Energy Storage Facilitybattery storagebattery storage0.2application withdrawnupdated Feb 2025Nov 2024—Feb 2025
Stafford Parkbattery storagebattery storage0.2approved, not builtupdated Sep 2025Nov 2024granted Sep 2025Sep 2025
Victoria Park Energy Storage Facilitybattery storagebattery storage0.2application withdrawnupdated Feb 2025Nov 2024—Feb 2025
Euston Way Energy Storage Facilitybattery storagebattery storage0.2application withdrawnupdated Feb 2025Nov 2024—Feb 2025
Radford House Energy Storage Facilitybattery storagebattery storage0.2approved, not builtupdated Sep 2025Nov 2024granted Sep 2025Sep 2025
Hortonwood Energy Storage Facilitybattery storagebattery storage0.2approved, not builtupdated Jul 2025Nov 2024granted Jul 2025Jul 2025
Ercall House, Stafford Park - Micro Energy Storage Facilitybattery storagebattery storage0.2approved, not builtupdated Sep 2025Jun 2025granted Aug 2025Sep 2025
Halesfield 1 Roundabout, Halesfield - Micro Energy Storage Facilitybattery storagebattery storage0.2refusedupdated Sep 2025Jun 2025refused Aug 2025Sep 2025
Makita Manufacturing Europerooftop solarrooftop solar0.2approved, not builtupdated Feb 2025Dec 2024granted Jan 2025Feb 2025
Cherwell Enterprise Park, Hortonwood 2 -Solar Panelsrooftop solarrooftop solar0.2application submittedMay 2026——
Myttons Solar Farmbattery storagebattery storage—approved, not built may be out of dateupdated Feb 2021Oct 2020granted Mar 2021Feb 2021
Twitch Hill, Cheswell Grange Farm Solar Farm & Battery Storagebattery storagebattery storage—under constructionupdated Jul 2024Dec 2021granted Jun 2022Jul 2024
Buildwas Bankbattery storagebattery storage—approved, not builtupdated Sep 2025Sep 2023granted Aug 2025Sep 2025
Tiddiecross Solar Farm & Battery Storagebattery storagebattery storage—approved, not builtupdated Feb 2026Dec 2024granted Jun 2025Feb 2026

Postcode districts in Telford and Wrekin

DistrictProjects within 10 kmPendingApprovedOperational
TF1453317
TF2423277
TF3413277
TF4413277
TF5433316
TF6334234
TF7353235
TF8323222
TF1022395

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Projects belong to Telford and Wrekin by location (nearest postcode to the REPD grid reference); decisions are counted by the planning authority named in REPD.