Energy Projects Near You

Myttons Solar Farm (49.9 MW)

Myttons Solar Farm is a 49.9 MW solar farm project in Telford and Wrekin, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 15 March 2021, not yet built; the record was last updated on 23 January 2021. REPD records the planning permission as expiring on 15 March 2024, but the project holds a Contracts for Difference award (AR4), so construction may have started. Check the planning authority's register for the latest position.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

49.9 MWsolar farm
approved, not builtmay be out of datestatus in REPD
23 January 2021record last updated
Telford and Wrekincouncil area

REPD records the planning permission as expiring on 15 March 2024, but the project holds a Contracts for Difference award (AR4), so construction may have started.

Planning timeline

DateStage
8 October 2020Application submitted
15 March 2021Planning permission granted
15 March 2024Permission expired

Project details

Technology
solar farm
Capacity
49.9 MW
Status (REPD)
approved, not built
Record last updated
23 January 2021
Operator or applicant
JBM Solar Projects Limited
Planning authority
Telford and Wrekin
Planning application reference
TWC/2020/0851
Site area
123.0 ha
Address (REPD)
Land N/O Roden Lane Farm
Council area (by location)
Telford and Wrekin
Time to decision
23 weeks
Contracts for Difference
AR4
REPD reference
8225

The scheme also includes battery storage, recorded separately in REPD (approved, not built).

Who decides

ApplicationsTelford and WrekinUK
Decided applications (solar, wind, battery)3410,236
Refused6 (18%)19%
Solar refused1 of 2512%
Battery storage refused5 of 916%
Median time from submission to decision12.7 weeks17.0 weeks
Appeals lodged / allowed2 / 5—

Other large projects within 10 km

ProjectTypeMWStatuskm
Haughmond Quarry - Uffington Solar Farmsolar farm25refused3.4
Sundorne Grovesolar farm20operational4.0
Church Farm, Withington Solar Farmsolar farm25approved, not built4.5
High Ercall Solar Farmsolar farm49.9approved, not built4.7
Bridge Farm, Uffingtonbattery storage8approved, not built4.9
Battery Energy Storagebattery storage100application submitted5.3
Pelham Road, Upton Magnabattery storage100application submitted5.6
Rushmoor Lane Farm (Cheshire Coppice)solar farm5operational7.2
Tiddiecross Solar Farm & Battery Storagesolar farm14approved, not built7.4

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.75, -2.6534).