Solar, wind and battery projects near Shrewsbury (SY3)
18 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of SY3 (Shropshire): 2 are waiting for a planning decision, 11 approved but not yet running, 4 operational. The largest live scheme is Battery Energy Storage (100 MW battery storage, application submitted on 24 February 2025, no decision recorded), 5.6 km away. Source: Renewable Energy Planning Database, July 2026 extract.
Projects within 10 km of SY3
Projects of 1 MW and more (10)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Condover (Green Farm)solar farm | solar farm | 10.2 | operationalupdated Apr 2015 | Sep 2013 | granted Jan 2014 | Apr 2015 | Shropshire | 5.6 |
| Battery Energy Storagebattery storage | battery storage | 100 | application submittedupdated Mar 2025 | Feb 2025 | — | Mar 2025 | Shropshire | 5.6 |
| Bridge Farm, Uffingtonbattery storage | battery storage | 8 | approved, not built may be out of dateupdated Jan 2024 | Jan 2023 | granted Apr 2023 | Jan 2024 | Shropshire | 5.6 |
| Sundorne Grovesolar farm | solar farm | 20 | operationalupdated Apr 2015 | Mar 2014 | granted Aug 2014 | Apr 2015 | Shropshire | 5.9 |
| Haughmond Quarry - Uffington Solar Farmsolar farm | solar farm | 25 | refusedupdated Jun 2024 | Mar 2024 | refused Jun 2024 | Jun 2024 | Shropshire | 6.6 |
| Berrington Farmsolar farm | solar farm | 30 | approved, not builtupdated May 2025 | Sep 2022 | granted May 2025 | May 2025 | Shropshire | 6.7 |
| Pelham Road, Upton Magnabattery storage | battery storage | 100 | application submittedupdated Jul 2025 | May 2025 | — | Jul 2025 | Shropshire | 7.5 |
| Condover Airfieldsolar farm | solar farm | 12.3 | operationalupdated May 2015 | Aug 2014 | granted Nov 2014 | May 2015 | Shropshire | 8.0 |
| Pitchfordsolar farm | solar farm | 10.2 | operationalupdated Aug 2015 | Aug 2014 | granted Nov 2014 | Aug 2015 | Shropshire | 9.5 |
| Myttons Solar Farmsolar farm | solar farm | 49.9 | approved, not built may be out of dateupdated Jan 2021 | Oct 2020 | granted Mar 2021 | Jan 2021 | Telford and Wrekin | 9.9 |
Smaller schemes under 1 MW, mostly rooftop solar (8)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Royal Shrewsbury Hospital, Mytton Oak Roadrooftop solar | rooftop solar | 0.8 | approved, not builtupdated Apr 2025 | Feb 2025 | granted Mar 2025 | Apr 2025 | Shropshire | 1.8 |
| Royal Shrewsbury Hospital, Mytton Oak Road Solar Canopysolar farm | solar farm | — | approved, not builtupdated Sep 2025 | Jul 2025 | granted Aug 2025 | Sep 2025 | Shropshire | 1.8 |
| Brassey Road - Micro Energy Storage Facilitybattery storage | battery storage | 0.2 | approved, not builtupdated Apr 2024 | Feb 2024 | granted Mar 2024 | Apr 2024 | Shropshire | 2.3 |
| Severn Hospicesolar farm | solar farm | 0.4 | approved, not builtupdated May 2024 | Apr 2024 | granted Sep 2024 | May 2024 | Shropshire | 3.0 |
| Shrewsbury Collegerooftop solar | rooftop solar | 0.7 | approved, not builtupdated Apr 2026 | Jan 2026 | granted Feb 2026 | Apr 2026 | Shropshire | 3.5 |
| Caterpillar Factory, Lancaster Roadrooftop solar | rooftop solar | 0.4 | approved, not builtupdated Mar 2025 | Nov 2024 | granted Jan 2025 | Mar 2025 | Shropshire | 4.2 |
| Benbow Business Park - Roof Monted Solar PV Systemrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Nov 2023 | Sep 2023 | granted Nov 2023 | Nov 2023 | Shropshire | 5.4 |
| Myttons Solar Farmbattery storage | battery storage | — | approved, not built may be out of dateupdated Feb 2021 | Oct 2020 | granted Mar 2021 | Feb 2021 | Telford and Wrekin | 9.9 |
Distance from the average position of the SY3 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.
By type
| Type | All | Pending | Approved | Operational | Refused | MW in pipeline |
|---|---|---|---|---|---|---|
| Solar farm | 9 | 0 | 4 | 4 | 1 | 80.3 |
| Rooftop solar | 4 | 0 | 4 | 0 | 0 | 2 |
| Battery storage | 5 | 2 | 3 | 0 | 0 | 208 |
MW in pipeline: pending, approved and under-construction capacity.
How Shropshire decides solar, wind and battery applications
| Applications | Shropshire | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 98 | 10,236 |
| Refused | 22 (22%) | 19% |
| Solar refused | 20 of 78 | 12% |
| Onshore wind refused | 2 of 3 | 45% |
| Battery storage refused | 0 of 17 | 16% |
| Median time from submission to decision | 15.2 weeks | 17.0 weeks |
| Appeals lodged / allowed | 10 / 5 | — |
Is the status up to date?
32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near SY3, 3 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.