Condover (Green Farm) (10.2 MW solar farm)

Condover (Green Farm) is a 10.2 MW solar farm project in Shropshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 24 March 2015; the record was last updated on 20 April 2015.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

10.2 MWsolar farm
operationalstatus in REPD
20 April 2015record last updated
Shropshirecouncil area

Planning timeline

DateStage
3 September 2013Application submitted
9 January 2014Planning permission granted
1 November 2014Construction started
24 March 2015Operational

Project details

Technology
solar farm
Capacity
10.2 MW
Status (REPD)
operational
Record last updated
20 April 2015
Operator or applicant
NextEnergy Solar Fund
Planning authority
Shropshire
Planning application reference
13/03519/FUL
Site area
24.5 ha
Address (REPD)
Land east of Cound Brook, Gree, Green Farm, Condover, Shrewsbury, Shropshire, SY5 7DA
Council area (by location)
Shropshire
Time to decision
18 weeks
REPD reference
1485

Who decides

ApplicationsShropshireUK
Decided applications (solar, wind, battery)9810,236
Refused22 (22%)19%
Solar refused20 of 7812%
Onshore wind refused2 of 345%
Battery storage refused0 of 1716%
Median time from submission to decision15.2 weeks17.0 weeks
Appeals lodged / allowed10 / 5—

Other large projects within 10 km

ProjectTypeMWStatuskm
Berrington Farmsolar farm30approved, not built1.5
Condover Airfieldsolar farm12.3operational2.7
Pitchfordsolar farm10.2operational4.0
Battery Energy Storagebattery storage100application submitted6.2
Pelham Road, Upton Magnabattery storage100application submitted6.6
Bridge Farm, Uffingtonbattery storage8approved, not built6.8
Haughmond Quarry - Uffington Solar Farmsolar farm25refused8.4
Sundorne Grovesolar farm20operational8.8
Church Farm, Withington Solar Farmsolar farm25approved, not built9.3

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.6569, -2.7298).