Energy Projects Near You

Pitchford (10.2 MW solar farm)

Pitchford is a 10.2 MW solar farm project in Shropshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 29 March 2015; the record was last updated on 27 August 2015.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

10.2 MWsolar farm
operationalstatus in REPD
27 August 2015record last updated
Shropshirecouncil area

Planning timeline

DateStage
1 August 2014Application submitted
21 November 2014Planning permission granted
19 December 2014Construction started
29 March 2015Operational

Project details

Technology
solar farm
Capacity
10.2 MW
Status (REPD)
operational
Record last updated
27 August 2015
Operator or applicant
Lightsource Renewable Energy
Planning authority
Shropshire
Planning application reference
14/03464/FUL
Site area
20.4 ha
Address (REPD)
Stockbatch, Pitchford, Shrewsbury, Shropshire
Council area (by location)
Shropshire
Time to decision
16 weeks
REPD reference
2211

Who decides

ApplicationsShropshireUK
Decided applications (solar, wind, battery)9810,236
Refused22 (22%)19%
Solar refused20 of 7812%
Onshore wind refused2 of 345%
Battery storage refused0 of 1716%
Median time from submission to decision15.2 weeks17.0 weeks
Appeals lodged / allowed10 / 5—

Other large projects within 10 km

ProjectTypeMWStatuskm
Condover Airfieldsolar farm12.3operational1.6
Berrington Farmsolar farm30approved, not built3.6
Condover (Green Farm)solar farm10.2operational4.0
Pelham Road, Upton Magnabattery storage100application submitted9.3
Battery Energy Storagebattery storage100application submitted9.6

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.6223, -2.7131).