Energy Projects Near You

Solar, wind and battery projects near Shrewsbury (SY5)

12 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of SY5 (Shropshire): 7 approved but not yet running, 5 operational. The largest live scheme is Berrington Farm (30 MW solar farm, approved on 2 May 2025, not yet built), 8.5 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

12projects within 10 km
0awaiting a decision
7approved, not running
5operational

Projects within 10 km of SY5

Projects of 1 MW and more (7)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Bath Mews, Minsterleybattery storagebattery storage10approved, not builtupdated Sep 2024Mar 2024granted Jul 2024Sep 2024Shropshire6.3
Condover (Green Farm)solar farmsolar farm10.2operationalupdated Apr 2015Sep 2013granted Jan 2014Apr 2015Shropshire7.0
Condover Airfieldsolar farmsolar farm12.3operationalupdated May 2015Aug 2014granted Nov 2014May 2015Shropshire7.3
Hayford Farm - extensionsolar farmsolar farm8.2operationalupdated Sep 2015Apr 2014granted Aug 2014Sep 2015Shropshire8.3
Berrington Farmsolar farmsolar farm30approved, not builtupdated May 2025Sep 2022granted May 2025May 2025Shropshire8.5
Hayford Farmsolar farmsolar farm8.9operationalupdated Sep 2015Sep 2012granted Dec 2012Sep 2015Shropshire8.6
Pitchfordsolar farmsolar farm10.2operationalupdated Aug 2015Aug 2014granted Nov 2014Aug 2015Shropshire8.8
Smaller schemes under 1 MW, mostly rooftop solar (5)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Royal Shrewsbury Hospital, Mytton Oak Roadrooftop solarrooftop solar0.8approved, not builtupdated Apr 2025Feb 2025granted Mar 2025Apr 2025Shropshire6.9
Royal Shrewsbury Hospital, Mytton Oak Road Solar Canopysolar farmsolar farm—approved, not builtupdated Sep 2025Jul 2025granted Aug 2025Sep 2025Shropshire6.9
Severn Hospicesolar farmsolar farm0.4approved, not builtupdated May 2024Apr 2024granted Sep 2024May 2024Shropshire7.9
Brassey Road - Micro Energy Storage Facilitybattery storagebattery storage0.2approved, not builtupdated Apr 2024Feb 2024granted Mar 2024Apr 2024Shropshire8.4
Shrewsbury Collegerooftop solarrooftop solar0.7approved, not builtupdated Apr 2026Jan 2026granted Feb 2026Apr 2026Shropshire9.1

Distance from the average position of the SY5 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm8035030.4
Rooftop solar202001.4
Battery storage2020010.2

MW in pipeline: pending, approved and under-construction capacity.

How Shropshire decides solar, wind and battery applications

ApplicationsShropshireUK
Decided applications (solar, wind, battery)9810,236
Refused22 (22%)19%
Solar refused20 of 7812%
Onshore wind refused2 of 345%
Battery storage refused0 of 1716%
Median time from submission to decision15.2 weeks17.0 weeks
Appeals lodged / allowed10 / 5—

All projects in Shropshire

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Check the council's planning register for the latest decision.