Energy Projects Near You

Hayford Farm - extension (8.2 MW solar farm)

Hayford Farm - extension is an 8.2 MW solar farm project in Shropshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 26 March 2015; the record was last updated on 2 September 2015.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

8.2 MWsolar farm
operationalstatus in REPD
2 September 2015record last updated
Shropshirecouncil area

Planning timeline

DateStage
28 April 2014Application submitted
26 August 2014Planning permission granted
1 February 2015Construction started
26 March 2015Operational

Project details

Technology
solar farm
Capacity
8.2 MW
Status (REPD)
operational
Record last updated
2 September 2015
Operator or applicant
Green Power
Planning authority
Shropshire
Planning application reference
14/01760/FUL
Site area
18.0 ha
Address (REPD)
Hayford Farm Westbury Shrewsbury
Council area (by location)
Shropshire
Time to decision
17 weeks
REPD reference
1995

Who decides

ApplicationsShropshireUK
Decided applications (solar, wind, battery)9810,236
Refused22 (22%)19%
Solar refused20 of 7812%
Onshore wind refused2 of 345%
Battery storage refused0 of 1716%
Median time from submission to decision15.2 weeks17.0 weeks
Appeals lodged / allowed10 / 5—

Other large projects within 10 km

ProjectTypeMWStatuskm
Hayford Farmsolar farm8.9operational0.3
Bath Mews, Minsterleybattery storage10approved, not built5.3

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.6868, -2.942).