Energy Projects Near You

Bath Mews, Minsterley (10 MW battery storage)

Bath Mews, Minsterley is a 10 MW battery storage project in Shropshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 26 July 2024, not yet built; the record was last updated on 2 September 2024.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

10 MWbattery storage
approved, not builtstatus in REPD
2 September 2024record last updated
Shropshirecouncil area

Planning timeline

DateStage
19 March 2024Application submitted
26 July 2024Planning permission granted

Project details

Technology
battery storage (stand-alone storage)
Capacity
10 MW
Status (REPD)
approved, not built
Record last updated
2 September 2024
Operator or applicant
Fig Power
Planning authority
Shropshire
Planning application reference
24/00889/FUL
Address (REPD)
North Of Bath Mews Minsterley
Council area (by location)
Shropshire
Time to decision
18 weeks
Name in REPD
Bath Mews, Minsterley - Battery Storage Facility
REPD reference
16074

Earlier applications for this site

ApplicationMWSubmittedOutcome
Bath Mews, Minsterley 22/01897/FUL1020 May 2022withdrawn 1 November 2022
Bath Mews, Minsterley 23/01031/FUL109 March 2023replaced by a revised application

Who decides

ApplicationsShropshireUK
Decided applications (solar, wind, battery)9810,236
Refused22 (22%)19%
Solar refused20 of 7812%
Onshore wind refused2 of 345%
Battery storage refused0 of 1716%
Median time from submission to decision15.2 weeks17.0 weeks
Appeals lodged / allowed10 / 5—

Other large projects within 10 km

ProjectTypeMWStatuskm
Hayford Farm - extensionsolar farm8.2operational5.3
Hayford Farmsolar farm8.9operational5.7

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.6398, -2.925).