Energy Projects Near You

Solar, wind and battery projects near Shrewsbury (SY4)

12 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of SY4 (Shropshire): 1 is waiting for a planning decision, 7 approved but not yet running, 3 operational. The largest live scheme is Myttons Solar Farm (49.9 MW solar farm, approved on 15 March 2021, not yet built; REPD status may be out of date), 8.7 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

12projects within 10 km
1awaiting a decision
7approved, not running
3operational

Projects within 10 km of SY4

Projects of 1 MW and more (7)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Harmer Hill, Webscottsolar farmsolar farm1application submittedupdated May 2026Apr 2026—May 2026Shropshire1.8
Sansaw Business Park, Hadnallrooftop solarrooftop solar1approved, not builtupdated Apr 2022Apr 2022granted May 2022Apr 2022Shropshire2.9
Charity Farm (Burlton Solar Farm)solar farmsolar farm14.4operationalupdated May 2020Jun 2014granted Sep 2014May 2020Shropshire4.7
Land To The North Of Moor Farmsolar farmsolar farm3.8operationalupdated Sep 2017May 2015granted Jan 2016Sep 2017Shropshire7.5
Sundorne Grovesolar farmsolar farm20operationalupdated Apr 2015Mar 2014granted Aug 2014Apr 2015Shropshire7.7
Myttons Solar Farmsolar farmsolar farm49.9approved, not built may be out of dateupdated Jan 2021Oct 2020granted Mar 2021Jan 2021Telford and Wrekin8.7
Haughmond Quarry - Uffington Solar Farmsolar farmsolar farm25refusedupdated Jun 2024Mar 2024refused Jun 2024Jun 2024Shropshire9.0
Smaller schemes under 1 MW, mostly rooftop solar (5)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Benbow Business Park - Roof Monted Solar PV Systemrooftop solarrooftop solar0.2approved, not builtupdated Nov 2023Sep 2023granted Nov 2023Nov 2023Shropshire6.4
Caterpillar Factory, Lancaster Roadrooftop solarrooftop solar0.4approved, not builtupdated Mar 2025Nov 2024granted Jan 2025Mar 2025Shropshire7.7
Kenwick Lodge, Cockshuttsolar farmsolar farm0.3approved, not built may be out of dateupdated Nov 2022Sep 2022granted Oct 2022Nov 2022Shropshire8.6
Myttons Solar Farmbattery storagebattery storage—approved, not built may be out of dateupdated Feb 2021Oct 2020granted Mar 2021Feb 2021Telford and Wrekin8.7
Severn Hospicesolar farmsolar farm0.4approved, not builtupdated May 2024Apr 2024granted Sep 2024May 2024Shropshire9.2

Distance from the average position of the SY4 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm8133151.6
Rooftop solar303001.6
Battery storage101000

MW in pipeline: pending, approved and under-construction capacity.

How Shropshire decides solar, wind and battery applications

ApplicationsShropshireUK
Decided applications (solar, wind, battery)9810,236
Refused22 (22%)19%
Solar refused20 of 7812%
Onshore wind refused2 of 345%
Battery storage refused0 of 1716%
Median time from submission to decision15.2 weeks17.0 weeks
Appeals lodged / allowed10 / 5—

All projects in Shropshire

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near SY4, 3 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.