Energy Projects Near You

Charity Farm (Burlton Solar Farm) (14.4 MW)

Charity Farm (Burlton Solar Farm) is a 14.4 MW solar farm project in Shropshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 2 August 2016; the record was last updated on 21 May 2020.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

14.4 MWsolar farm
operationalstatus in REPD
21 May 2020record last updated
Shropshirecouncil area

Planning timeline

DateStage
12 June 2014Application submitted
29 September 2014Planning permission granted
28 May 2016Construction started
2 August 2016Operational

Project details

Technology
solar farm
Capacity
14.4 MW
Status (REPD)
operational
Record last updated
21 May 2020
Operator or applicant
Lightsource Renewable Energy
Planning authority
Shropshire
Planning application reference
14/02537/FUL
Site area
35.6 ha
Address (REPD)
Land east of B4397, Charity Farm, Burlton, Shropshire
Council area (by location)
Shropshire
Time to decision
16 weeks
Contracts for Difference
AR1
REPD reference
2108

Who decides

ApplicationsShropshireUK
Decided applications (solar, wind, battery)9810,236
Refused22 (22%)19%
Solar refused20 of 7812%
Onshore wind refused2 of 345%
Battery storage refused0 of 1716%
Median time from submission to decision15.2 weeks17.0 weeks
Appeals lodged / allowed10 / 5—

Other large projects within 10 km

ProjectTypeMWStatuskm
Rednal Airfield, West Feltonbattery storage300approved, not built8.3

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.8244, -2.8096).