Rednal Airfield, West Felton (300 MW battery storage)

Rednal Airfield, West Felton is a 300 MW battery storage project in Shropshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 16 April 2026, not yet built; the record was last updated on 15 June 2026.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

300 MWbattery storage
approved, not builtstatus in REPD
15 June 2026record last updated
Shropshirecouncil area

Planning timeline

DateStage
7 May 2025Application submitted
16 April 2026Planning permission granted
16 April 2031Permission due to expire (unless work starts)

Project details

Technology
battery storage (stand-alone storage)
Capacity
300 MW
Status (REPD)
approved, not built
Record last updated
15 June 2026
Operator or applicant
Private Developer
Planning authority
Shropshire
Planning application reference
25/01250/FUL
Address (REPD)
Rednal Airfield Rednal West
Council area (by location)
Shropshire
Time to decision
49 weeks
Name in REPD
Rednal Airfield, West Felton - Battery Energy Storage
REPD reference
18028

Who decides

ApplicationsShropshireUK
Decided applications (solar, wind, battery)9810,236
Refused22 (22%)19%
Solar refused20 of 7812%
Onshore wind refused2 of 345%
Battery storage refused0 of 1716%
Median time from submission to decision15.2 weeks17.0 weeks
Appeals lodged / allowed10 / 5—

Other large projects within 10 km

ProjectTypeMWStatuskm
Charity Farm (Burlton Solar Farm)solar farm14.4operational8.3
Ebnal Lodgesolar farm5operational9.1

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.8364, -2.9309).