Energy Projects Near You

Ebnal Lodge (5 MW solar farm)

Ebnal Lodge is a 5 MW solar farm project in Shropshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 15 February 2017; the record was last updated on 4 December 2017.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

5 MWsolar farm
operationalstatus in REPD
4 December 2017record last updated
Shropshirecouncil area

Planning timeline

DateStage
23 September 2015Application submitted
23 December 2015Planning permission granted
12 December 2016Construction started
15 February 2017Operational

Project details

Technology
solar farm
Capacity
5 MW
Status (REPD)
operational
Record last updated
4 December 2017
Operator or applicant
Greencoat Capital
Planning authority
Shropshire
Planning application reference
15/03975/FUL
Site area
13.4 ha
Address (REPD)
Land At, Rhosygadfa, Gobowen, Oswestry
Council area (by location)
Shropshire
Time to decision
13 weeks
REPD reference
5834

Earlier applications for this site

ApplicationMWSubmittedOutcome
Ebnal Lodge Solar Farm 14/03946/FUL1510 October 2014refused 13 July 2015

Who decides

ApplicationsShropshireUK
Decided applications (solar, wind, battery)9810,236
Refused22 (22%)19%
Solar refused20 of 7812%
Onshore wind refused2 of 345%
Battery storage refused0 of 1716%
Median time from submission to decision15.2 weeks17.0 weeks
Appeals lodged / allowed10 / 5—

Other large projects within 10 km

ProjectTypeMWStatuskm
Trench Farmsolar farm7.2operational8.2
Rednal Airfield, West Feltonbattery storage300approved, not built9.1

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.9001, -3.0152).