Trench Farm (7.2 MW solar farm)

Trench Farm is a 7.2 MW solar farm project in Shropshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 30 March 2015; the record was last updated on 10 May 2016.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

7.2 MWsolar farm
operationalstatus in REPD
10 May 2016record last updated
Shropshirecouncil area

Planning timeline

DateStage
3 July 2014Application submitted
5 November 2014Planning permission granted
6 November 2014Construction started
30 March 2015Operational

Project details

Technology
solar farm
Capacity
7.2 MW
Status (REPD)
operational
Record last updated
10 May 2016
Operator or applicant
Lightsource Renewable Energy
Planning authority
Wrexham
Planning application reference
P/2014/0484
Site area
21.3 ha
Address (REPD)
Trench Farm, Red Hall Lane, Penley, Wrexham LL13 0NA
Council area (by location)
Shropshire
Time to decision
18 weeks
REPD reference
2079

Who decides

ApplicationsWrexhamUK
Decided applications (solar, wind, battery)2010,236
Refused3 (15%)19%
Solar refused2 of 1412%
Onshore wind refused1 of 145%
Battery storage refused0 of 516%
Median time from submission to decision21.8 weeks17.0 weeks
Appeals lodged / allowed2 / 2—

UK: all UK planning authorities. Counted under these REPD planning authority names: Newry, Mourne and Downe, Wrexham.

Other large projects within 10 km

ProjectTypeMWStatuskm
Ebnal Lodgesolar farm5operational8.2
Maelor Gasworks Solar Farm & Battery Storagesolar farm5.7approved, not built9.1
Williams Farmsolar farm5operational9.3

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.9454, -2.9179).