Energy Projects Near You

Williams Farm (5 MW solar farm)

Williams Farm is a 5 MW solar farm project in Wrexham, Wales. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 31 March 2016; the record was last updated on 28 July 2016.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

5 MWsolar farm
operationalstatus in REPD
28 July 2016record last updated
Wrexhamcouncil area

Planning timeline

DateStage
26 June 2015Application submitted
21 December 2015Planning permission granted
1 February 2016Construction started
31 March 2016Operational

Project details

Technology
solar farm
Capacity
5 MW
Status (REPD)
operational
Record last updated
28 July 2016
Operator or applicant
Solar Ventures
Planning authority
Wrexham
Planning application reference
P/2015/0463
Site area
10.0 ha
Address (REPD)
Williams Farm, Maelor Gas Works, Marchwiel, Wrexham
Council area (by location)
Wrexham
Time to decision
25 weeks
REPD reference
6172

Who decides

ApplicationsWrexhamUK
Decided applications (solar, wind, battery)2010,236
Refused3 (15%)19%
Solar refused2 of 1412%
Onshore wind refused1 of 145%
Battery storage refused0 of 516%
Median time from submission to decision21.8 weeks17.0 weeks
Appeals lodged / allowed2 / 2—

UK: all UK planning authorities. Counted under these REPD planning authority names: Newry, Mourne and Downe, Wrexham.

Other large projects within 10 km

ProjectTypeMWStatuskm
Maelor Gasworks Solar Farm & Battery Storagesolar farm5.7approved, not built0.3
Little Llwyn Onn Solar Farm & Battery Storagesolar farm9.9approved, not built2.3
Land north of Bryn Lanesolar farm6.4permission expired2.8
Land south of Francis Landsolar farm10permission expired3.2
Wrexham Social Housing PVrooftop solar5.4operational4.8
Land at Borras Hallsolar farm10abandoned4.9
Bronwylfa Road, Rhostyllenbattery storage400application submitted7.8
Plas Power Estate Solar Farmsolar farm57application submitted8.0
Trench Farmsolar farm7.2operational9.3

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (53.029, -2.9213).