Energy Projects Near You

Solar, wind and battery projects near Wrexham (LL14)

22 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of LL14 (Wrexham): 4 are waiting for a planning decision, 10 approved but not yet running, 8 operational. The largest live scheme is Bronwylfa Road, Rhostyllen (400 MW battery storage, application submitted on 8 March 2024, no decision recorded; REPD status may be out of date), 4.4 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

22projects within 10 km
4awaiting a decision
10approved, not running
8operational

Projects within 10 km of LL14

Projects of 1 MW and more (14)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Penycae Solar Farmsolar farmsolar farm5operationalupdated May 2016Jul 2015granted Oct 2015May 2016Wrexham0.5
Land Opposite Tyn Y Pistyllsolar farmsolar farm5operationalupdated Aug 2016Feb 2015granted May 2015Aug 2016Wrexham1.2
Bronwylfa Road, Rhostyllenbattery storagebattery storage400application submitted may be out of dateupdated Apr 2024Mar 2024—Apr 2024Wrexham4.4
Bronwylfa Reservoirsolar farmsolar farm3operationalupdated Jan 2016Apr 2014granted Jul 2014Jan 2016Wrexham4.5
Plas Power Estate Solar Farmsolar farmsolar farm57application submitted may be out of dateupdated Apr 2025Jun 2024—Apr 2025Wrexham5.4
Plas Power Estate Solar Farmbattery storagebattery storage57application submitted may be out of dateupdated Apr 2025Jun 2024—Apr 2025Wrexham5.4
Wrexham Social Housing PVrooftop solarrooftop solar5.4operationalupdated Oct 2012——Oct 2012Wrexham6.9
Knolton Farmhouse Cheese Solar Farmsolar farmsolar farm1operationalupdated Sep 2016Apr 2015granted Jun 2015Sep 2016Wrexham7.4
Berllandeg Farm, Rhoswielsolar farmsolar farm1.3approved, not builtupdated Jul 2025May 2025granted Jun 2025Jul 2025Shropshire8.1
Little Llwyn Onn Solar Farm & Battery Storagebattery storagebattery storage16approved, not builtupdated Jun 2022Jun 2022granted Mar 2023Jun 2022Wrexham8.1
Little Llwyn Onn Solar Farm & Battery Storagesolar farmsolar farm9.9approved, not builtupdated Jun 2022Jun 2022granted Mar 2023Jun 2022Wrexham8.1
Land NW Of Pickhill Bridge Farmsolar farmsolar farm3.6operationalupdated Dec 2017Apr 2015granted Jul 2015Dec 2017Wrexham9.3
Maelor Gasworks Solar Farm & Battery Storagesolar farmsolar farm5.7approved, not builtupdated Nov 2022Jul 2021granted Nov 2022Nov 2022Wrexham9.5
Williams Farmsolar farmsolar farm5operationalupdated Jul 2016Jun 2015granted Dec 2015Jul 2016Wrexham9.8
Smaller schemes under 1 MW, mostly rooftop solar (8)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
National Grid Legacy Substation, Bronwylfa Roadbattery storagebattery storage—approved, not builtupdated Aug 2023Mar 2023granted Jul 2023Aug 2023Wrexham4.3
Hillhead Road & Dundrum Road Wind Farmwind turbinewind turbine—application submittedMay 2026——Wrexham6.3
Plas Yolyn Solar Parksolar farmsolar farm—approved, not builtupdated May 2024Nov 2023granted May 2024May 2024Shropshire8.4
F Lloyd Penleyrooftop solarrooftop solar0.4operationalupdated Sep 2023——Sep 2023Wrexham9.1
Wonderbank, Brymbo Roadsolar farmsolar farm0.6approved, not builtupdated Jan 2026Nov 2024granted Dec 2025Jan 2026Wrexham9.3
Wonderbank, Brymbo Roadbattery storagebattery storage—approved, not builtupdated Jan 2026Nov 2024granted Dec 2025Jan 2026Wrexham9.3
Maelor Gasworks Solar Farm & Battery Storagebattery storagebattery storage—approved, not builtupdated Nov 2022Jul 2021granted Nov 2022Nov 2022Wrexham9.5
Land SE of, Spectrum Business Parkbattery storagebattery storage—approved, not built may be out of dateupdated Apr 2020Jun 2017granted Oct 2017Apr 2020Wrexham9.9

Distance from the average position of the LL14 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm12156074.5
Rooftop solar200200
Wind turbine110000
Battery storage72500473

MW in pipeline: pending, approved and under-construction capacity.

How Wrexham decides solar, wind and battery applications

ApplicationsWrexhamUK
Decided applications (solar, wind, battery)2010,236
Refused3 (15%)19%
Solar refused2 of 1412%
Onshore wind refused1 of 145%
Battery storage refused0 of 516%
Median time from submission to decision21.8 weeks17.0 weeks
Appeals lodged / allowed2 / 2—

UK: all UK planning authorities. Counted under these REPD planning authority names: Newry, Mourne and Downe, Wrexham.

All projects in Wrexham

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near LL14, 4 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.