Land Opposite Tyn Y Pistyll (5 MW solar farm)

Land Opposite Tyn Y Pistyll is a 5 MW solar farm project in Wrexham, Wales. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 22 December 2015; the record was last updated on 24 August 2016.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

5 MWsolar farm
operationalstatus in REPD
24 August 2016record last updated
Wrexhamcouncil area

Planning timeline

DateStage
10 February 2015Application submitted
12 May 2015Planning permission granted
16 October 2015Construction started
22 December 2015Operational

Project details

Technology
solar farm
Capacity
5 MW
Status (REPD)
operational
Record last updated
24 August 2016
Operator or applicant
Lightsource Renewable Energy
Planning authority
Wrexham
Planning application reference
P/2015/0092
Site area
10.7 ha
Address (REPD)
Land Opposite Tyn Y Pistyll, West of Delph Road, Penycae, Wrexham, Clwyd
Council area (by location)
Wrexham
Time to decision
13 weeks
REPD reference
5026

Who decides

ApplicationsWrexhamUK
Decided applications (solar, wind, battery)2010,236
Refused3 (15%)19%
Solar refused2 of 1412%
Onshore wind refused1 of 145%
Battery storage refused0 of 516%
Median time from submission to decision21.8 weeks17.0 weeks
Appeals lodged / allowed2 / 2—

UK: all UK planning authorities. Counted under these REPD planning authority names: Newry, Mourne and Downe, Wrexham.

Other large projects within 10 km

ProjectTypeMWStatuskm
Penycae Solar Farmsolar farm5operational0.7
Bronwylfa Road, Rhostyllenbattery storage400application submitted5.2
Plas Power Estate Solar Farmsolar farm57application submitted6.1
Wrexham Social Housing PVrooftop solar5.4operational8.0
Little Llwyn Onn Solar Farm & Battery Storagesolar farm9.9approved, not built9.3

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.9874, -3.0704).