Energy Projects Near You

Plas Power Estate Solar Farm (57 MW)

Plas Power Estate Solar Farm is a 57 MW solar farm project in Wrexham, Wales. Its status in the Renewable Energy Planning Database (July 2026 extract) is: application submitted on 11 June 2024, no decision recorded; the record was last updated on 14 April 2025. It is decided by the Welsh Government as a development of national significance. The application was submitted more than two years ago and is still shown as pending; it may have been decided since. Check the planning authority's register for the latest position.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

57 MWsolar farm
application submittedmay be out of datestatus in REPD
14 April 2025record last updated
Wrexhamcouncil area

The application was submitted more than two years ago and is still shown as pending; it may have been decided since. 32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided.

Planning timeline

DateStage
11 June 2024Application submitted

Project details

Technology
solar farm
Capacity
57 MW
Status (REPD)
application submitted
Record last updated
14 April 2025
Operator or applicant
Lightsource BP
Planning authority
Welsh Government (NSIP)
Planning application reference
DNS/3253253
Site area
136.0 ha
Address (REPD)
Plas Power Estate, Ruthin Road, Wrexham
Council area (by location)
Wrexham
REPD reference
7858

The scheme also includes 57 MW of battery storage, recorded separately in REPD (application submitted).

Who decides

It is decided by the Welsh Government as a development of national significance. Welsh Government (NSIP) refused 22% of 55 decided solar, wind and battery applications in REPD (median 67 weeks to a decision). Across all UK planning authorities 19% of 10,236 decided applications were refused.

Other large projects within 10 km

ProjectTypeMWStatuskm
Bronwylfa Road, Rhostyllenbattery storage400application submitted1.0
Wrexham Social Housing PVrooftop solar5.4operational3.3
Little Llwyn Onn Solar Farm & Battery Storagesolar farm9.9approved, not built5.7
Penycae Solar Farmsolar farm5operational5.7
Land Opposite Tyn Y Pistyllsolar farm5operational6.1
Land at Borras Hallsolar farm10abandoned7.3
Maelor Gasworks Solar Farm & Battery Storagesolar farm5.7approved, not built7.8
Williams Farmsolar farm5operational8.0
Land north of Bryn Lanesolar farm6.4permission expired8.4

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (53.039, -3.0394).