Penycae Solar Farm (5 MW)

Penycae Solar Farm is a 5 MW solar farm project in Wrexham, Wales. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 28 March 2016; the record was last updated on 26 May 2016.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

5 MWsolar farm
operationalstatus in REPD
26 May 2016record last updated
Wrexhamcouncil area

Planning timeline

DateStage
15 July 2015Application submitted
5 October 2015Planning permission granted
28 January 2016Construction started
28 March 2016Operational

Project details

Technology
solar farm
Capacity
5 MW
Status (REPD)
operational
Record last updated
26 May 2016
Operator or applicant
SBC Renewables
Planning authority
Wrexham
Planning application reference
P/2015/0546
Site area
10.3 ha
Address (REPD)
Land To East And West Of, Benn, The Grange Plas, Penycae, Wrexham, Clwyd
Council area (by location)
Wrexham
Time to decision
12 weeks
REPD reference
5376

Who decides

ApplicationsWrexhamUK
Decided applications (solar, wind, battery)2010,236
Refused3 (15%)19%
Solar refused2 of 1412%
Onshore wind refused1 of 145%
Battery storage refused0 of 516%
Median time from submission to decision21.8 weeks17.0 weeks
Appeals lodged / allowed2 / 2—

UK: all UK planning authorities. Counted under these REPD planning authority names: Newry, Mourne and Downe, Wrexham.

Other large projects within 10 km

ProjectTypeMWStatuskm
Land Opposite Tyn Y Pistyllsolar farm5operational0.7
Bronwylfa Road, Rhostyllenbattery storage400application submitted4.8
Plas Power Estate Solar Farmsolar farm57application submitted5.7
Wrexham Social Housing PVrooftop solar5.4operational7.4
Little Llwyn Onn Solar Farm & Battery Storagesolar farm9.9approved, not built8.7
Maelor Gasworks Solar Farm & Battery Storagesolar farm5.7approved, not built10.0

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.9888, -3.0596).